This week it was announced that essential carriageway repairs would be carried out on Wawne Road from Monday October 25.
The work will be carried out overnight, between 7.30pm and 6.30am and is expected to take up to a week to complete. The Wawne Road/Sutton Road (Wawne) roundabout will be closed off during these hours.
Councillor Dean Kirk, portfolio holder for roads, highways and transport, said: “The renewal of this section of Wawne Road is essential in order to provide a safe and even surface for traffic.”
Read more here.
A breakdown of planned works taking place across Hull has been detailed below:
Location | Start date | Completion date | Details of work | Organisation |
A63 Castle Street – From St James Street to Market Place
|
May 2020 | May 2025 | Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGV’s in city centre. | National Highways |
A63 Castle St Scheme – Closures | May 2020 | May 2025 | Full lane closures east & west bound. | Highways England |
Stoneferry Rd Scheme – Woodhall Street to Lorraine Ave | 1 April 2021 | 28 May 2022 | Installation of the Stoneferry Road corridor capital program scheme. | HCC MP&I (Colas) |
Stoneferry Rd Scheme – Woodhall Street to Chamberlain Road |
18 October 2021 | 30 October 2021 | Relocation of gullies. Road closure from 7pm to 6am. | Hull City Council, MP&I |
Stoneferry Rd Scheme – Chamberlain Road to Bandstand Roundabout | 23 April 2021 | 25 June 2022 | Installation of the Stoneferry Road Corridor scheme | Hull City Council, MP&I |
Stoneferry Corridor – Resurfacing full scheme | 20 Sept 2021 | Jan 2021 | Carriageway resurfacing throughout the whole scheme | Hull City Council, MP&I |
Stoneferry corridor – Woodhall Street to Chamberlain Road | 18 October 2021 | 29 October 2021 | Reconstruction of the carriageway | Hull City Council, MP&I |
Stoneferry Corridor – Ferry Lane | 01 November 2021 | 06 November 2021 | Road cosure 7pm-6am. Ferry Lane – EastBound only from Ferry Lane Bridge to the Roundabout with Stoneferry Road | HCC – Colas |
Stoneferry Corridor – Stoneferry Road | 01 November 2021 | 06 November 2021 | Road Closure 7pm-6am Stoneferry Road – NorthBound only between Ferry Lane Roundabout and Bandstand Roundabout | HCC – Colas |
Wiltshire Road (full length)
|
14 June 21 | 17 Oct 21 | Excavate existing concrete carriageway and carry out any required concrete repairs. | HCC – MP&I |
Brunswick Arcade (Beverley Road) | 16 August 2021 | November 2022 | Lane closures | Hull City Council |
Lowgate | 20 September 2021 | 8 April 2022 | Paving of footpaths | Hull City Council |
Spring Bank West | 25 October 2021 |
3 December 2021 | Upgrading network | NGN |
Beverley Road LEP (Whole length – split into phases as shown below) | 23 August 2021 | December 2021 | Create cycle lanes & junction widening | Hull City Council, MP&I |
Beverley Road | 22 August 2021 | 17 November 2021 | Construction of off-line cycle track. Mizzen Road to Hall Road Inbound | Hull City Council, MP&I |
Beverley Road | 31 August 2021 | 21 October 2021 | Construction of Cycle Way – City Centre Boundary to Mizzen Road Inbound. | Hull City Council, MP&I |
Beverley Road | 14 October 2021 | 04 November 2021 | Construction of off line cycle track. Hall Road to City Boundary Outbound | HCC – MP&I |
Beverley Road – Fountain Road | 6 September 2021 | 22 October 2021 | Implementation of cycle scheme. Work suspended during Hull Fair – white lines to be completed during w/c October 18 (one night’s work | Hull City Council. MP&I |
Air Street | 27 September 2021 | 22 October 2021 | Essential gas work upgrades | NGN |
Holderness Road Victor Street to Southcoates – Phases 1-8 |
27 September 2021 | September 2022 | Full footway reconstruction scheme | Hull City Council, MP&I |
Caroline Street | 17 October 2021 | 18 October 2021 | Emergency – gas escape | NGN |
Bellfield Avenue | 20 September 2021 | 22 October 2021 (extended) | Essential repairs, footway and carriageway | YW |
Hawthorne Avenue | 11 October 2021 | 15 October 2021 | New connections | YW |
Hessle Road | 14 October 2021 | 19 October 2021 | Network Connections – lane closure | YW |
Saltshouse Road | 25 October 2021 | 12 January 2022 | Installation of two new pedestrian refuge islands between Dunvegan Road and Clearview Close | Hull City Council. MP&I |
Bowlalley Lane | 18 October 2021 | 17 December 2021 | Footway Scheme. Extended to include Carriageway | HCC- MP&I |
Hawthorne Ave | 18 October 2021 | 27 October 2021 | Pot Hole repairs – whole street | HCC – HWO |
Lowgate Footway Scheme – Market Place | 22 October 2021 | 22 December 2021 | Footway repair scheme | HCC – MP&I |
Calvert Lane | 25 October 2021 | 29 October 2021 | Enable water connections to new buildings | YW |
Hopewell Road | 25 October 2021 | 19 December 2021 | Junction Staveley Road to Taylor Avenue | HCC – MP&I |
Spring Bank West | 25 October 2021 | 03 December 2021 | Upgrading network – lane closures | NGN |
Bond Street / Albion Street | 08 November 2021 | 22 November 2021 | BHS, Survey works – 8pm – 6am signals at junction of Bond / George Street and Bond / Albion Street. Various Lane closures | HCC |
Wawne Road – Cumbrian Way roundabout | 25 October 2021 | 29 October 2021 | Carriageway reconstruction – night Road Closure 7.30pm to 6.30pm | HCC – MPI |
New Bridge Road | 26 October 2021 | 26 October 2021 | Inspection of rail over road bridge via ladder. Hours of works 9am-5pm | NETWORK RAIL |