Work to improve the paving in Lowgate and Market Place is now complete.
The new footpaths benefit from a high-quality natural stone finish, further enhancing the appearance of the Old Town and making it more accessible for everyone.
The road has now reopened to traffic in both directions. While some snagging work may continue into next week, there will be no restrictions on traffic.
Below is a breakdown of roadworks taking place across Hull over the next few weeks. All works are subject to change. For the latest updates:
A63 improvement scheme - St James Street to Market Place | 01 May 2020 | 01 May 2025 | Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. | National Highways |
A63 improvement scheme - Commercial Road | 26 October 2021 | 30 April 2022 | Enable H&S and safe systems of works for operatives working on the scheme. | National Highways |
Beverley Road | 07 March 2022 | 22 April 2022 | Gas Main replacement scheme. Inbound from city Boundary to Mizzen Road. Lane Closure | Northern Gas Networks |
Beverley Road - Brunswick Arcade | 04 October 2021 | 01 September 2022 | Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022. | HCC - MP&I |
Bishop Lane | 16 May 2022 | 19 May 2022 | Install new water supply connection. Full road closure. Local diversion in place. | Yorkshire Water |
Charles Street | 04 April 2022 | 29 April 2022 | Works between Francis Street and Bridlington Avenue, including work in the carriageway and footpath. Removal of existing line markings, installation of new gullies and kerbs to construct off-road cycle track. New surfacing and line markings. Multi-way signals, to be manned at peak times. | HCC - MP&I |
Great Union Street | 23 May 2022 | 26 June 2022 | Resurfacing / concrete repairs. Full road closure. Access to be maintained at all times for businesses via A63 / Clarence Street. | HCC - MP&I |
Hall Road | 26 April 2022 | 26 April 2022 | Telecoms pole maintenance. Two-way signals in place from 9.30am-3.30pm. | O2 (GS Hall) |
Hessle Road (12-month Scheme) | 23 August 2021 | 04 September 2022 | Footway reconstruction. | HCC - MP&I |
Holderness Road (Victor St to Southcoates) (PHASES 1-8) | 04 January 2022 | 11 September 2022 | Full footway reconstruction scheme. | MP&I - Highways Strategy & Design |
Hopewell Road | 14 March 2022 | 24 April 2022 | Concrete repairs and carriageway resurfacing. Road closure from Slaveley Road junction to Taylor Avenue. | HCC - MP&I |
Howdale Road - Phase 2 | 26 April 2022 | 04 May 2022 | Trench repair on 2nd half of carriageway. Multi-way signals. Junction of Oaktree Drive. 8am start on Sunday. Traffic management to be removed once concrete has cured. | Streetscene Highway Operations |
Ings Road | 09 May 2022 | 19 May 2022 | Lane closure in place entrance between 9am and 3pm from the junction of Eglington Avenue to Crooked Billet car park entrance. | Northern Gas Network |
Stoneferry Rd Scheme - Woodhall Street to Lorraine Street | 01 April 2021 | 01 August 2022 | Major Improvement Scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed. | HCC - MP&I |
Stoneferry Rd Scheme - Chamberlain Road to Bandstand Roundabout | 23 April 2021 | 01 August 2022 | Major improvement scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed. | HCC - MP&I / Colas |
Stoneferry Rd Scheme - Sutton Road | 11 April 2022 | 21 April 2022 | Road closure from Holwell Roundabout to western end of Bericap factory. Works will take place overnight 7pm to 6am. Access to Jet garage and Aldi will be maintained during the works. Work will not take place over the bank holiday weekend and will resume overnight on Tues 19th. | HCC - MP&I COLAS |
Stoneferry Rd Scheme - Sutton Road | 20 April 2022 | 22 April 2022 | Removal of existing splitter islands in the junction of Sutton Road and Leads Road. night. Multi-way signals. Works will take place 7pm to 6am. | HCC - MP&I COLAS |
Stoneferry Rd Scheme - Leads Road | 25 April 2022 | 29 July 2022 | Renew footpaths and kerbs. Leads Road closed westbound between Rotterdam Road and Bandstand Roundabout during works. | HCC - MP&I COLAS |
Stoneferry Rd Scheme - Leads Road | 29 July 2022 | 01 August 2022 | Carriageway resurfacing. Leads Road closed in both directions between Rotterdam Road and Bandstand Roundabout from 7pm on Friday 29 July to 6am on Monday August 1. | HCC - MP&I COLAS |
Wincolmlee | 18 April 2022 | 29 April 2022 | Works originally postponed due to gas leak. Power main replacement scheme. Multiway signals, junction of Wincomlee/ Air Street / Bank Side. | Northern Power Grid |