Hull is in the midst of a huge transformation to its transport system, with major works taking place across the city, including the A63, Stoneferry Corridor and critical utility repairs.
The current works are being undertaken by a number of organisations in addition to Hull City Council, including Highways England and Northern Gas Networks, with scheduled works from Northern Powergrid.
The works are coordinated across the network to avoid pinch points, however the works currently taking place are essential.
Motorists are advised to plan their journey before travelling using One.Network, and to keep up-to-date with Stoneferry Corridor works download the Hello Travaux app on the App Store on Google Play.
Councillor Dean Kirk, portfolio holder for transportation, roads, highways and flood prevention, said: “We understand that roadworks can be frustrating for motorists, however these works are essential if we are to improve our transport system for better and safer journeys in the future. We apologise for any inconvenience to drivers in the meantime.”
Below is a breakdown of the roadworks currently taking place in Hull.
Location | Start date | Completion date | Details of work | Organisation | Current status |
A63 Castle Street – From St James Street to Market Place.
|
May 2020 | May 2025 | Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGV’s in city centre | Highways England | On track |
A63 Castle Street | 14 June 2021 | 3 July 2021 | Full Lane closures east & west bound | Highways England | On track |
Daltry Street and Roger Millward Way | 7 July | Friday 9 July | Overnight lane closures (8pm – 6am) | Highways England | On track |
Stoneferry Road – Foster St to Sutton Road | Commenced | 28 May 2022 | Installation of the Stoneferry Road Corridor capital program scheme | Hull City Council | On track |
Woodhall Street | 10 May 2021 | 16 July 2021 | Installation of the Stoneferry Road Corridor capital program scheme | Hull City Council | Extended by 22 days |
Holwell Road to Mount Pleasant junction (Stoneferry Corridor works) | 23 April 2021 | 25 June 2022 | Installation of the Stoneferry Road Corridor | Hull City Council | On track |
Cottingham Road | 24 May 2021 | 27 June 2021 | Roadworks reconstruction & resurfacing
|
Hull City Council | Extended by 9 days |
Cranbrook Avenue | 24 May 2021 | 11 July 2021 | Roadworks reconstruction & resurfacing
|
Hull City Council | Extended by 35 days |
Greenwood Avenue | 24 May 2021 | 16 July 2021 | Replacement of gas pipes in footpaths | Northern Gas Networks | On track |
Wiltshire Road | 14 June 2021 | 22 August 2021 | Excavate existing concrete carriageway and carry out any required concrete repairs
|
Hull City Council | On track |
South Street, Carr Lane & Paragon Street | 14 June 2021 | 30 July 2021 | Essential gas works | Northern Gas Networks | Additional works agreed |
Humber Street & High Street | 21 June 2021 | 7 Oct 2021 | Reconstruction of footpaths and road surface | Hull City Council | On track |
Clarence Street | 30 June 2021 | 6 July 2021 | Cycle lanes, anti-skid & line removal | Hull City Council | On track |
Wincolmlee | 30 June 2021 | 6 July 2021 | Essential works – new connection | Northern Powergrid | On track |
Dunvegan Road | 28 June 2021 | 15 August 2021 | Essential footway repairs | Hull City Council | On track |
Witham | 7 July 2021 | 9 July 2021 | Cycle lanes, anti-skid & line removal | Hull City Council | Planned |
Priory Way | October 2021 | August 2022 | Major widening and construction of three signalised junctions | Hull City Council | Planned |
Sutton Road (Stoneferry Corridor works) | June 2021 | December 2021 | Reconstruction of junction | Hull City Council | Planned |
Priory Road | 08 Aug 2021 | 20 Sept 2021 | Carriageway & footway re-construction & bus lanes/ parking bays | Hull City Council | Planned |
Lowgate (outside Guildhall) | 19 July 2021 | 19 July 2021 | Crane required to access the clock tower | Hull City Council | Planned |
Lowgate | September 2021 | March 2022 | Footway repair scheme | Hull City Council | Planned |
Air Street | Oct 2021 | Oct 2021 | Essential Gas Works – upgrades | Northern Gas Networks | Planned |
Holderness Road | 19 July 2021 | 30 July 2021 | Installation of cycle lane | Hull City Council | Planned |