Hull City Council weekly traffic and travel update – 27 October

Roadworks signs

Here is the latest breakdown of scheduled and emergency works taking place across Hull over the next few weeks. All works are subject to change. For the latest updates:

LocationStart dateDue dateSummary of worksUtility/HCC
A63 improvement scheme – St James Street to Market Place01-May-2001-May-25Full infrastructure change. Lane and road closures until completion of scheme. National Highways
A63 improvement scheme – Commercial Road26-Oct-2130-Apr-24Enable H&S and safe systems of works for operatives working on the scheme. Road closure in place.National Highways
Beverley Road26-Oct-2330-Oct-23Telecoms installation outside 888-852. Lane closure in place from 9.30am to 3.30pm.Connexin
Barnes Way06-Nov-2312-Nov-23Investigation works close to the junction. Multi-way signals in place.Gas Transportation Company
Brook Street12-Nov-2312-Nov-23Remembrance Day 2023. To ensure the smooth running of the parade and service, the road closure will be in place from 6am to 1pm.Hull City Council (events)
Clifford Avenue23-Oct-2327-Oct-23Installing new water supply. Road closure in place from 8am Monday 23 October to 6pm Friday 27 October.Yorkshire Water
County Road North31-Oct-2302-Nov-23Duct works. Two-way signals in place.Yorkshire Water
Endike Lane30-Oct-2301-Nov-23Telecoms installation outside the Lord Nelson pub. Multi-way signals from 9.30am to 3.30pm.Hutchison 3G Limited
Ferensway12-Nov-2312-Nov-23Remembrance Day 2023. To ensure the smooth running of the parade and service, the road closure will be in place from 6am to 1pm.Hull City Council (events)
Gillett Street25-Oct-2329-Oct-23Installing new mobile telecoms pole and cabinet outside Turbo Systems. Road closure in place.Hutchison 3G Ltd
Gibraltar Road08-Nov-2309-Nov-23Telecoms fault, investigation works. One way road closure in place from 8pm to 6am.Cornerstone telecommunications
Holderness Road30-Oct-2317-Nov-23Telecoms installation at the junction of Sherburn Street over Holderness road to outside 311. Multi-way signals in place.Grain
Inglemire Lane02-Nov-2304-Nov-23Telecoms installation opposite Oldstead Avenue. Multi-way signals manned during traffic sensitive times.
Hutchison 3G Ltd
Leads Road23-Oct-2306-Nov-23Carriageway resurfacing and reconstruction outside 85-Wickes. Multi-way signals in place.Hull City Council (Highway Operatives)
Raich Carter Way22-Oct-2304-Nov-23To carry out repairs to the combined non-slip and waterproofing to the lifting spans of the Ennerdale bridge decks. Contraflow traffic management will be in place.Hull City Council (Bridges Team)
North Street12-Nov-2312-Nov-23Remembrance Day 2023. To ensure the smooth running of the parade and service, the road closure will be in place from 6am to 1pm.Hull City Council (events)
Princes Avenue17-Oct-2306-Nov-23Telecoms installation from 38 to 85 Princes Avenue. Multi-way signals in place from 9.30am to 3.30pm only.
Grain
Preston Road02-Nov-2310-Nov-23Telecoms installation at the junction of Marfleet Lane. Lane closure in place.Northern Gas Networks
Prospect Street12-Nov-2312-Nov-23Remembrance Day 2023. To ensure the smooth running of the parade and service, the road closure will be in place from 6am to 1pm.Hull City Council (events)
Priory Road06-Nov-2317-Nov-23Strengthen the culvert between Flaxton and Setting Road. Two-way signals in place.Hull City Council (Bridges Team)
Walker Street06-Nov-2307-Nov-23Carriageway and centre island repairs outside 6 Lovat Close. Road closure in place.Hull City Council (Highway Operatives)
West Street12-Nov-2312-Nov-23Remembrance Day 2023. To ensure the smooth running of the parade and service, the road closure will be in place from 6am to 1pm.Hull City Council (events)