Hull’s ambitious project to improve its transport system continues this week as essential major works take place across the city.
They include works at the A63 and Stoneferry Corridor and also critical utility repairs.
The works are being undertaken by organisations including Highways England, Northern Gas Networks and Hull City Council, with scheduled works from Northern Powergrid.
Councillor Dean Kirk, portfolio holder for transportation, roads, highways and flood prevention, said: “Work in Cranbrook Avenue should complete this weekend, easing congestion in this part of the city.
“We understand that roadworks can be frustrating for motorists, however these works are essential if we are to improve our transport system for better and safer journeys in the future. We apologise for any inconvenience to drivers in the meantime.”
Motorists are advised to plan their journey before travelling using One.Network, and to keep up-to-date with Stoneferry Corridor works download the Hello Travaux app on the App Store on Google Play.
From Monday 28 June there will also be overnight closures on the A63 (8pm – 6am) for 5 nights as part of the Castle street works.
During this time, to ensure access to all properties is maintained, the works on Humber Street will be removed.
Below is a breakdown of the roadworks currently taking place in Hull –
Location | Start Date | Due Date | Reason | Utility/HCC Name | Current Status | Work Type | Traffic Impact Assessment | Notes & any Diversion Overview | ||||
Works Commenced | ||||||||||||
A63 Castle Street – From St James Street to Market Place.
|
May 2020 | May 2025 | Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGV’s in city centre. | Highways England | On Track | Planned | Operating under a Development Control Order which gives additional powers to Highways England to change things as required. HCC having to respond accordingly | |||||
A63 Castle Street | 14 June 2021 | 3 July 2021 | Full Lane closures east & west bound. | Highways England | On Track | Planned | Significant |
|
||||
Stoneferry Road – Foster St to Sutton Road | Commenced | 28 May 2022 | Installation of the Stoneferry Road Corridor capital program scheme. | HCC MP&I (Colas) | On Track | Planned | Significant | Lane closures plus portable traffic signals at Woodhall Street junction (Traffic signals on until 28 May to allow new drainage to be installed new the railway bridge) | ||||
Woodhall Street | 10 May 2021 | 16 July 2021 | Installation of the Stoneferry Road Corridor capital program scheme. | HCC MP&I (Colas) | Extended by 22 days | Planned | Significant | Portable Traffic Signals at Woodhall Street – these are manually operated during peak times. Extension requested to scheme of works. | ||||
Holwell Road to Mounty Pleasant junction | 23 April 2021 | 25 June 2022 | Installation of the Stoneferry Road Corridor | HCC MP&I | On Track | Planned | Significant | Lane & footpath closures plus portable pedestrian crossing in use. | ||||
Cottingham Road | 24 May 2021 | 27 June 2021 | Roadworks reconstruction & resurfacing.
|
HCC MP&I | Extended by 9 days | Planned | Moderate | Lane Closures. Changing TM to Traffic lights (2 way) Lights Manned. | ||||
Cranbrook Avenue | 24 May 2021 | 11 July 2021 | Roadworks reconstruction & resurfacing.
|
HCC MP&I | OVERRUN – Extended by 35 days | Planned | Moderate | Road Closure. Local diversion in place. | ||||
Greenwood Avenue | 24 May 2021 | 16 July 2021 | Replacement of gas pipes in footpaths. | Northern Gas Networks | On Track | Planned | Minor | Closures of some section of footpath. No planned carriageway incursion. | ||||
Stockholm Road & West Carr Lane | 08 June 2021 | 25 June 2021 | Essential Works | Northern Powergrid | On Track | Planned | Low | From Junction of West Carr Lane to Outside Substation ( Footway, Carriageway). Works no in footway. | ||||
Wiltshire Road (Full Length) | 14 June 2021 | 22 August 2021 | Excavate existing concrete carriageway and carry out any required concrete repairs.
|
HCC – MP&I | On Track | Planned | Moderate | Traffic Control will be Give and Take. | ||||
South Street, Carr Lane & Parragon Street | 14 June 2021 | 02 July 2021 | Essential Gas Works | Northern Gas Networks | On Track | Planned | Moderate | Road Closure at South Street. Traffic Signals on jnct of South Street/Anlaby Road. Paragon Street change too, 2 way traffic for duration of works. Car parking revoked temporarily. | ||||
Humber Street & High Street | 21 June 2021 | 07 Oct 2021 | Reconstruction of footpaths and road surface. | HCC MP&I | On Track | Planned | Moderate | Will include; Road Closure, lane closures and footpath closure. Works will halt for Humber Street Sesh ( 14.09.21). Start date delayed by 1 week, due to NGN on lowgate and A63 closures EB& WB. | ||||
Fairfax Avenue | 22 June 2021 | 28 June 2021 | Emergency Water Repairs – Burst Main | YW | Emergency | Emergency | Moderate | Burst Water Main. | ||||
Major Works Planned to start in next two weeks | ||||||||||||
Witham | 05 July 21 | 09 July 21 | Line Removal, Anti Skid & Lining Works | HCC – MPI | Agreed | Planned | Moderate | Road Closed – full length of Witham inbound 7 pm to 11 pm. Diversion route onto Clarence Street and Great Union Street | ||||
Wincolmlee | 30 June 2021 | 06 July 2021 | Essential Works – New Connection. | Northern Powergrid | Agreed | Planned | Moderate | Working 9.30am – 5 pm , 2 way lights. First day set up after 9.30, to avoid peak traffic. | ||||
Clarence Street | 30 June 2021 | 06 July 2021 | Cycle Lanes & Anti Skid& Line Removal | HCC – MP&I | Agreed | Planned | Moderate – Low | Mixed TM solutions, using Lane Closures, stop and go boards at junctions. | ||||
Hawthorn Ave – Chalk Lane Level Crossing | 27 June 21 | 29 Jun 21 | Rail Corrosion Inspections | Network Rail | Agreed | Planned | Moderate – Low | Night time closures, 23.55 – 05.10, each night. | ||||
Dunvegan Road | 28 June 2021 | 15 August 2021 | Essential Footway Repairs. | HCC – MPI | Agreed | Planned | Moderate- Low | Eastern Fooway from Saltshouse Road – East Carr Road, with Lane Closures. To be completed in phases, to enable residents accesses. | ||||
Major Works on the Radar | ||||||||||||
Priory Way | October 2021 | August 2022 | Major widening and construction of three signalised junctions. | HCC – MP&I | Planned | Planned | Significant | TM detail not available. Will include lane closures and possible road closures. Potential to affect HE trunk road network. | ||||
Sutton Road | Awaiting Start Dates | Awaiting Dates | Reconstruction of junction. Stoneferry Corridor works | HCC – MP&I | Planned | Planned | Significant | Traffic control (multi-way signals) | ||||
Priory Road | 08 Aug 2021 | 20 Sept 2021 | Carriageway & Footway re-construction & bus lanes/ Parking Bays | HCC – MP&I | Planning Stage | Planning | Significant | Diversion Routes – large route to include County Road North, Bricknell Ave, through Cottingham. Will impact on the Bus routes. | ||||
Lowgate (outside Guildhall) | 19 July 2021 | 19 July 2021 | Crane required to access the clock tower. Essential works | HCC – NPS | Planning Stage | Planning | Significant | Diversion routes currently being discussed. | ||||
Lowgate Footway scheme | Sept 2021 | March 2022 | Footway repair scheme | HCC – MPI | Planning Stage | Planning | Moderate | Lane closures SB & NB required on lowgate, from Market Place to Alfred Gelder Street, with Diversions onto A63 | ||||
Air Street | Oct 2021 | Oct 2021 | Essential Gas Works – upgrades | NGN | Planning Stage | Planning | Significant | 4 week road closure, with significant diversion route, potentially into pre-existing diversions already on the network. (Stoneferry scheme). |