Keep up-to-date on the roadworks across the city

Weekly roadworks update – May 20

A short section of Beverley Road will be reduced to one lane in each direction from next week.

From Sunday 22 May, emergency work will be carried out to repair two gully connections that are in danger of collapse between Trafalgar Street and Leonard Street. This work is expected to last seven days.

The two gullies in danger of collapse

From Monday 30 May, protective hoardings will be re-erected between Norfolk Street and Trafalgar Street to allow work to continue on the Brunswick Arcade restoration project.

Andy Bell, Head of Highways Infrastructure at Hull City Council, said: “We had hoped to be able to delay the gully works until next year, but we believe a collapse is imminent.

“From observations on site, the carriageway can be seen to flex quite badly when HGVs and buses pass across the gullies.

“Carrying out these emergency works now will ensure the road remains safe for all highway users.”

Below is a breakdown of roadworks taking place across Hull over the next few weeks. All works are subject to change. For the latest updates:

LocationStart dateDue dateSummary of worksUtility/HCC name
A63 improvement scheme - St James Street to Market Place01 May 202001 May 2025Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre.National Highways
A63 improvement scheme - Commercial Road26 October 202130 April 2024Enable H&S and safe systems of works for operatives working on the scheme.National Highways
Beverley Road - Brunswick Arcade04 October 202101 April 2023Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022.HCC - MP&I
Calvert Lane16 May 202210 July 2022Carriageway resurfacing scheme from approximately 50m north of Boundary Way to Calvert Lane fire station. Road closed. Diversion in place. Access to be maintained at all times.HCC - MP&I
Charles Street04 April 202215 June 2022Works between Francis Street and Bridlington Avenue, including work in the carriageway and footpath. Removal of existing line markings, installation of new gullies and kerbs to construct off-road cycle track. New surfacing and line markings. Multi-way signals, to be manned at peak times. HCC - MP&I
Gillshill Road24 May 202207 June 2022Works between Sutton House Road and Ings Road junction to establish new gas connection. Two-way signals.Northern Gas Network
Great Union Street23 May 202226 June 2022Resurfacing / concrete repairs. Full road closure. Access to be maintained at all times for businesses via A63 / Clarence Street.HCC - MP&I
Hessle Road (12-month Scheme)23 August 202104 September 2022Footway reconstruction.HCC - MP&I
Holderness Road (Victor St to Southcoates) (PHASES 1-8)04 January 202211 September 2022Full footway reconstruction scheme.MP&I - Highways Strategy & Design
Howdale Road16 May 202227 May 2022Date changed. Trench repair on 2nd half of carriageway. Multi-way signals. Junction of Oaktree Drive. 8am start on Sunday. Traffic management to be removed once concrete has cured.Streetscene Highway Operations
Ings Road09 May 202227 May 2022Lane closure in place entrance between 9am and 3pm from the junction of Eglington Avenue to Crooked Billet car park entrance.Northern Gas Network
National Avenue18 May 202228 May 2022New power supply outside Caradon Heating. Two-way signals.Northern Powergrid
Park Street06 June 202217 June 2022Replacement of gas main. Road closure. Westbound road closure (Caughey Street to Spring Bank). No access from Spring Bank. Access from Park Street to Spring Bank still available.Northern Gas Network
Princes Avenue25 May 202227 May 2022Surfacing and line marking. Two-way signals in place 24 hours a day.HCC - MP&I
Priory Way01 April 202231 March 2023Major improvement scheme.HCC - MP&I
Stoneferry Rd Scheme - Woodhall Street to Lorraine Street01 April 202101 July 2022Major Improvement Scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall Street junction are now completed.HCC - MP&I
Stoneferry Rd Scheme - Chamberlain Road to Bandstand Roundabout23 April 202101 July 2022Major improvement scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall Street junction are now completed.HCC - MP&I / Colas
Stoneferry Rd Scheme - Leads Road25 April 202229 July 2022Renew footpaths and kerbs. Leads Road closed westbound between Rotterdam Road and Bandstand Roundabout during works.

HCC - MP&I COLAS
Stoneferry Rd Scheme - Leads Road29 July 202201 August 2022Carriageway resurfacing. Leads Road closed in both directions between Rotterdam Road and Bandstand Roundabout from 7pm on Friday 29 July to 6am on Monday August 1.HCC - MP&I COLAS
Stoneferry Rd Scheme - Sutton Road03 May 202201 July 2022Reconstruction of the new junction under temporary traffic lights to enable removal of the existing permanent traffic signals. Multi-way signals to run in phases to help minimise disruption. Leads Road / Sutton Road junction.HCC - MP&I