A63 improvement scheme – St James Street to Market Place | 01-May-20 | 01-May-25 | Full infrastructure change. Lane and road closures until completion of scheme. | National Highways |
A63 improvement scheme – Commercial Road | 26-Oct-21 | 30-Apr-24 | Enable H&S and safe systems of works for operatives working on the scheme. Road closure in place. | National Highways |
A63 Castle Street – between Daltry Street and Roger Millward Way | 10-Mar-24 | 06-April-24 | Various overnight closures to complete work at Market Place and Queen Street junction and other essential works. To find our more, visit https://nationalhighways.co.uk/our-roads/yorkshire-and-north-east/a63-castle-street/ | National Highways |
A63 – Queen Street | 11-Mar-24 | 10-May-24 | Castle Street improvement scheme. Full closure of Queen Street on slip (traffic will have no access on to the A63 westbound) Full diversion route will be in place. | National Highways |
Alexandra Road | 05-Feb-24 | 18-Mar-24 | Carriageway reconstruction and resurfacing from Beverley Road to Leonards Avenue. Road closure in place. | Hull City Council (Major Projects) |
Barnes Way | 11-Mar-24 | 20-Mar-24 | Utility connections outside the entrance to the new housing development. Two-way signals in place. | Gas Transportation Company |
Beverley Road | 11-Mar-24 | 15-Mar-24 | Gully repairs from Hall Road to City Boundary. Lane closures in place. | Hull City Council |
Cleveland Street | 08-Mar-24 | 08-Mar-24 | Cutting of new detection loop damaged by on going work. Multi-way signals in place. | Hull City Council (Major Projects) |
Collage Street | 10-Mar-24 | 12-March-24 | New infrastructure build at the junction of Lowgate. Multi-way signals to be manually controlled at all times. | MS3 |
County Road North | 04-Mar-24 | 16-Mar-24 | To strengthen and repair the existing structure. Two-way signals in place. | Hull City Council (Bridges Team) |
Coventry Road | 04-Mar-24 | 17-May-24 | Installing a new pipe, manhole and connecting onto the existing combined sewer network. Part of the Living with Water Aqua Green Scheme. Road closure in place. | Yorkshire Water |
Holderness Road | 10-Mar-24 | 11-Mar-24 | Cable connection outside Park Health Centre. Lane closure in place. | Yorkshire Water |
James Reckitt Avenue | 12-Mar-24 | 14-Mar-24 | Telecoms installation at the junction of Dunscombe park. Two-way signals in place. | Grain |
Mount Pleasant | 10-Mar-24 | 10-Mar-24 | Telecoms maintenance between Dansom lane and Courtney Street. Two-way signals in place. | Hutchison 3g Limited |
Manor Road | 05-Feb-24 | 26-Apr-24 | Installing a new pipe, manhole, and connecting onto the existing combined sewer network outside number 82 and 84. Part of the Living with Water Aqua Green Scheme. Road closure in place. | Yorkshire Water |
Moorhouse Road | 11-Mar-24 | 14-Jun-24 | Installing a new pipe and manhole on the carriageway and connecting onto the combined sewer. Part of the Living with Water Aqua Green Scheme. Road closure in place. | Yorkshire Water |
Spring Bank West | 04-Mar-24 | 12-Mar-24 | Telecoms Installation at the junction of Albert Avenue. Lane closure in place. | Grain |
Stoneferry Road | 12-Mar-24 | 14-Mar-24 | Gully lid repair at the junction of Foster Street. Lane closure in place from 9pm to 6am only. | Yorkshire Water |
Wingfield Road | 26-Feb-24 | 11-Mar-24 | Carriageway reconstruction. Traffic control (priority working) in place. | Hull City Council (Major Projects) |