Beginning Monday 10 January, Rawling Way will see some resurfacing and concrete repairs, with road closure taking place between 7.30pm and 6.30am to minimise disruption.
Works to Barham Road to resurface the road and repair concrete, which were due to finish on Sunday 23 January, will now be completed by Sunday 6 February. The road will be closed throughout the duration of the works.
Below is a breakdown of roadworks taking place across Hull over the next few weeks:
Location | Start Date | Due Date | Reason | Utility/HCC Name |
A63 improvement scheme – Commercial Road | 26/10/21 | 30/4/22 | Enable H&S and safe systems of works for operatives working on the scheme | National Highways |
A63 improvement scheme – St James Street to Market place | 1/5/20 | 1/5/25 | Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. | National Highways |
A63 improvement scheme – Daltry Street to Rodger Milward Way | 18/1/22 | 21/1/22 | Road will be closed from 8pm – 6am. | National Highways |
Barham Road | 29/11/21 | 6/2/22 | Carriageway resurfacing and concrete repairs. | HCC – MP&I |
Beverley Road | 5/1/22 | 14/1/22 | Surfacing to cycle track and footpath, topsoil to verge followed by line removal and new lining to centralise lanes, plus anti-skid at Downfield Avenue Junction, which will remain open. | HCC – MP&I |
Beverley Road – Brunswick Arcade | 4/10/21 | 1/9/22 | Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022. | HCC – MP&I |
Beverley Road – Mizzen Road to Windle Avenue | 4/1/22 | 11/2/22 | Construction of new cycle track and footpath on the existing footpath and verge. Lane closure. | MP&I ARBPMLTD |
Eglinton Avenue | 21/2/22 | 4/3/22 | Road closure due to gas mains replacement on Ings Road. | Northern Gas Network |
Hessle Road (12-month Scheme) | 23/8/21 | 4/9/22 | Footway reconstruction. | HCC – MP&I |
Holderness Road (Victor St to Southcoates) (PHASES 1-8) | 4/1/22 | 11/9/22 | Full footway reconstruction scheme. | MP & I – Highways Strategy & Design |
Holderness Road – Holland Street to Sherburn Street | 4/1/22 | 13/2/22 | Footway reconstruction and repaving. | MP & I |
Holderness Road | 24/1/22 | 11/2/22 | Excavate and locate cable, joint new cable and reinstate excavations for new connection. | SWB MASS MARKET Z3 |
Ings Road | 14/2/22 | 11/3/22 | Works to footway and carriageway. | Northern Gas Network |
Leads Road | 17/1/22 | 21/1/22 | Affecting Truro Close junction, repairs to road. | MS3 Networks Ltd |
Lowgate Footway Scheme – East side | 17/1/22 | 8/4/22 | Alfred Gelder Street to North Church Side, road closures between 7.30pm and 6.00am, Monday to Saturday. | HCC – MP&I |
Lowgate Footway Scheme – Lowgate | 1/11/21 | 10/1/22 | Footway repair scheme. Closed northbound from A63 to North Church Side. A63 slip road closed. Lane open southbound from Alfred Gelder Street to A63. | HCC – MP&I |
Lowgate Footway Scheme – Market Place | 22/10/21 | 17/1/22 | Footway repair scheme. East footway – no carriageway incursion. Except on occasions, parking bays removed to provide walkway. | HCC – MP&I |
Portland Place | 4/1/22 | 21/1/22 | Essential gas repairs. Road closure, traffic to follow diversion. | Northern Gas Network |
Priory Way | 22/2/22 | 23/2/22 | Major widening and construction of three signalised junctions. | HCC – MP&I |
Rawling Way | 10/1/22 | 17/1/22 | Resurfacing and concrete repairs. Proposed closure between 7.30pm and 6.30am. | HCC – MP&I |
Saltshouse Road | 1/11/21 | 12/1/22 | Installation of two new pedestrian refuge islands between Dunvegan Road and Clear View Close. | HCC-MP&I |
Savoy Road | 14/2/22 | 3/3/22 | Road closure due to gas mains replacement on Ings Road. | Northern Gas Network |
Silver Street | 4/1/22 | 31/1/22 | Road closure due to istallation of automated bollards. | HCC – MP&I |
Stoneferry Rd Scheme – Woodhall Street to Lorraine Avenue | 1/4/21 | 28/5/22 | Major Improvement Scheme commissioned by HCC – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed | HCC – MP&I |
Stoneferry Rd Scheme – Chamberlain Road to Bandstand roundabout | 23/4/21 | 25/6/22 | Major improvement scheme commissioned by HCC – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed | HCC – MP&I COLAS |
Stoneferry Rd Scheme | TBC/2/21 | TBC/2/21 | Resurfacing to mainline carriageway at the Ferry Lane roundabout. Overnight road closure. | HCC – MP&I COLAS |
Wincolmlee (Phase 1) | 13/12/21 | 17/1/22 | Essential work to upgrade power supply. Multi-way signals, to be manned during traffic-sensitive times. All traffic management to be removed during Christmas closedown. | Northern Power Grid |
Wincolmlee (Phase 2) | 31/1/22 | 18/3/22 | New connection and cable upgrades. Road closure. | Northern Power Grid |