Roadworks sign
A number of road closures will be in place for Remembrance Sunday.

Weekly roadworks update – November 5

Essential overnight resurfacing works on Stoneferry Road and Ferry Lane will continue into next week, owing to unforeseen circumstances.

This phase of the work, part of the multi-million-pound Stoneferry improvement scheme, will now end at 6am on Tuesday 9 November.

The carriageway will be closed overnight on Ferry Lane from the River Hull bridge (eastbound) to Stoneferry Road/Ferry Lane roundabout, and on Stoneferry Road (northbound) from Stoneferry Road/Ferry Lane roundabout to Bandstand roundabout. Read our previous story here.

Subsequent resurfacing works may consequently be delayed.

The next phase of overnight resurfacing on Stoneferry Road, from Ferry Lane roundabout to Chamberlain Road roundabout, will now begin at 7pm on Tuesday 9 November. Read our previous story here.

Councillor Dean Kirk, portfolio holder for transportation, roads and highways, said: “While any delays are regrettable, unfortunately they are sometimes unavoidable.

“We endeavour to complete these works as quickly and efficiently as possible and apologise for any inconvenience caused.”

A breakdown of planned works taking place across Hull has been detailed below:

Location Start Date Due Date Reason Utility/HCC Name
A63 improvement scheme – Commercial Road 26/10/21 30/4/22 Enable H&S and safe systems of works for operatives working on the scheme National Highways
A63 Castle Street scheme –  St James Street to  Market place 1/5/20 1/5/25 Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. National Highways
Barham Road 29/11/21 23/1/22 Carriageway Resurfacing and concrete repairs HCC – MP&I
Beverley Road  (split into phases) 23/8/21 3/12/21 Implementation of cycle scheme. Queens Road/ Beverley Road and Cottingham Rd/Clough Road junctions HCC – MP&I
Beverley Road Inbound (Phase 1) 31/8/21 12/11/21 Construction of cycle way. City Centre boundary to Mizzen Road.  Works mainly in the verge with kerb works in channel. Lane Closure 24/7 HCC – MP&I
Beverley Road 14/10/21 19/11/21 Construction of off-line cycle track. Hall Road to City Boundary outbound. Lane closure throughout duration of works. HCC – MP&I
Beverley Road 22/10/21 3/12/21 Implementation of cycle scheme. Mizzen road to Hall Road Inbound. 9.30am to 3.30pm lane closures HCC – MP&I
Beverley Road 18/10/21 25/10/21 New gas connection. Closure of bus lane Northern Gas Network
Beverley Road, Freetown Way & Spring Bank West 8/11/21 19/11/21 Variable messaging sign installation in footways. This scheme is to create the foundations and install the poles. Work taking place over 10 sites (most have no carriageway incursion) over a 10-day period. Each site will require a maximum of three to four visits and traffic management will be removed at the end of each visit. Traffic-sensitive sites will only be live between 9.30am and 3.30pm per visit. HCC – MP&I
Bond Street / Albion Street 8/11/21 22/11/21 BHS, Survey works. 8pm – 6am signals at junction of Bond / George Street & Bond / Albion Street. Various lane closures HCC – MP&I
Bowlalley Lane 18/10/21 17/12/21 Footway Scheme. Extended to include carriageway. Road closure HCC – MP&I
Calvert Lane 1/11/21 10/11/21 Final resurfacing works. HCC – Streetscene Signals
Hall Road 11/11/21 11/11/21 Installation of telecoms mast off junction with access road to superstore. 9.30am – 3.30pm. Works expected to take no longer than three hours. HCC – MP&I
Hall Road 15/11/21 24/11/21 Multiple carriageway repair works to be carried out consecutively. Temporary traffic lights. HCC – Streetscene HWO
Hessle Road (12 month Scheme) 23/8/21 4/9/22 Footway scheme, reconstructions HCC – MP&I
Holderness Road  (Victor St to Southcoates) (PHASES 1-8) 27/9/21 1/11/22 Full footway reconstruction scheme. HCC – MP&I
Holwell Road (between Honiton Road and Bude Road) 8/11/21 17/11/21 Multiple carriageway repair works to be carried out consecutively. Temporary traffic lights. HCC – Streetscene HWO
Lowgate Footway Scheme – Market Place 20/9/21 22/12/21 Footway repair scheme. From A63 up towards North Church site west footway. Some parking bays removed for walkway HCC – MP&I
Lowgate Footway Scheme – Market Place 22/10/21 22/12/21 Footway repair scheme. East footway – no carriageway incursion. Except on occasions, parking bays removed to provide walkway HCC – MP&I
Saltshouse Road 8/11/21 12/1/22 Installation of two new pedestrian refuge islands between Dunvegan Road and Clear View Close Northern Gas Network
Spring Bank West 25/10/21 3/12/21 Upgrading network. Opposite Albert Ave to Tile Giant (footway, carriageway) HCC – Streetscene Signals
Stoneferry Rd Scheme – Chamberlain Road to Bandstand Roundabout 23/4/21 25/6/22 Major improvement scheme commissioned by HCC  – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed HCC – MP&I  COLAS
Stoneferry Rd Scheme – Woodhall Street to Lorraine Ave 1/4/21 28/5/22 Major Improvement Scheme commissioned by HCC  – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed HCC – MP&I
Stoneferry Rd Scheme – Woodhall Street to Chamberlain Road 18/10/21 30/10/21 Relocation of gullies. Road closure between Woodhall street and Chamberlain Road. 7pm to 6am. HCC – MP&I  COLAS
Stoneferry Rd Scheme – Ferry Lane 1/11/21 9/11/21 Road surfacing. Ferry Lane – eastbound only from Ferry Lane bridge to the roundabout with Stoneferry Road. Weeknight closures 7pm-6am HCC – MP&I  COLAS
Stoneferry Rd Scheme – Ferry Lane Roundabout to Bandstand Roundabout. 1/11/21 9/11/21 Road surfacing. Stoneferry Road – northbound only between Ferry Lane roundabout and Bandstand roundabout. Weeknight closures 7pm-6am HCC – MP&I  COLAS
Stoneferry Rd Scheme – Ferry Lane 15/11/21 20/11/21 Road Surfacing. Ferry Lane westbound from Stoneferry Road Roundabout to Ferry Lane Bridge (Carriageway) HCC – MP&I  COLAS
Stoneferry Rd Scheme – Ferry Lane roundabout to Chamberlain Road roundabout 9/11/21 13/11/21 Stoneferry Corridor southbound only from Ferry Lane Roundabout to Chamberlain Roundabout. Weeknight closures 7pm-6am HCC – MP&I  COLAS