Major restoration work to Brunswick Arcade on Beverley Road will begin next week in the interest of public safety.
From Monday 11 October, Beverley Road will be reduced to two lanes between Norfolk Street and Trafalgar Street, meaning all vehicles will share the carriageway. Traffic flow will be maintained in both directions. The work will continue until spring 2022.
Councillor Daren Hale, leader of Hull City Council, said: “This will mean a single lane in both directions and the closure of the bus lane for a small section of Beverley Road. I know as a road user of this route this is frustrating, but we cannot take any chances with public safety.”
Read more here.
A breakdown of planned works taking place across Hull has been detailed below:
Location | Start date | Completion date | Details of work | Organisation |
A63 Castle Street – From St James Street to Market Place
|
May 2020 | May 2025 | Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGV’s in city centre. | National Highways |
A63 Castle St Scheme – Closures | May 2020 | May 2025 | Full lane closures east & west bound. | Highways England |
Stoneferry Rd Scheme – Woodhall Street to Lorraine Ave | 1 April 2021 | 28 May 2022 | Installation of the Stoneferry Road corridor capital program scheme. | HCC MP&I (Colas) |
Stoneferry Rd Scheme – Woodhall Street to Chamberlain Road |
4 October 2021 | 16 October 2021 | Relocation of gullies. Road closure from 7pm to 6am. | Hull City Council, MP&I |
Stoneferry Rd Scheme – Chamberlain Road to Bandstand Roundabout | 23 April 2021 | 25 June 2022 | Installation of the Stoneferry Road Corridor scheme | Hull City Council, MP&I |
Stoneferry Corridor – Resurfacing full scheme | 20 Sept 2021 | Jan 2021 | Carriageway resurfacing throughout the whole scheme | Hull City Council, MP&I |
Stoneferry corridor – Woodhall Street to Chamberlain Road | 18 October 21 | 29 October 21 | Reconstruction of the carriageway | Hull City Council, MP&I |
Wiltshire Road (full length)
|
14 June 21 | 17 Oct 21 | Excavate existing concrete carriageway and carry out any required concrete repairs. | HCC – MP&I |
Commercial Road | 2 August 2021 | 25 October 2021 | A63 Improvement scheme | National Highways |
Brunswick Arcade (Beverley Road) | 16 August 2021 | November 2022 | Lane closures from October 11 | Hull City Council |
Lowgate | 20 September 2021 | 8 April 2022 | Paving of footpaths | Hull City Council |
Spring Bank West | 25 October 2021 |
3 December 2021 | Upgrading network | NGN |
Beverley Road LEP (Whole length – split into phases as shown below) | 23 August 2021 | December 2021 | Create cycle lanes & junction widening | Hull City Council, MP&I |
Beverley Road
(Phase 1) |
23 August 2021 | 12 October 2021 – extended | Construction of off lane cycle track. Greenwood Avenue to Hall Road Outbound. | Hull City Council, MP&I |
Beverley Road
(Phase 3) |
21 September 2021 | 13 October 2021 | Construction of off line cycle track. Greenwood Avenue to City Boundary Outbound | Hull City Council, MP&I |
Beverley Road
(Phase 4) |
22 August 2021 | 17 November 2021 | Construction of off line cycle track. Mizzen Road to Hall Road Inbound | Hull City Council, MP&I |
Beverley Road
Inbound – Phase 1 |
31 August 2021 | 21 October 2021 | Construction of Cycle Way | Hull City Council, MP&I |
Beverley Road – Fountain Road | 6 September 2021 | 22 October 2021 | Implementation of cycle scheme. Work suspended during Hull Fair – white lines to be completed during w/c October 18 (one night’s work | Hull City Council. MP&I |
Air Street | 27 September 2021 | 22 October 2021 | Essential gas work upgrades | NGN |
Silver Street | 4 January 2022 | 31 January 2022 | Installing automatic bollards | Hull City Council |
Holderness Road Victor Street to Southcoates – Phases 1-8 |
27 September 2021 | September 2022 | Full footway reconstruction scheme | Hull City Council, MP&I |
Anlaby Road | 10 October 2021 | 10 October 2021 | Puffin crossing trial | Hull City Council, MP&I |
Lowgate/Market Place | 14 October 2021 | 14 October 2021 | Puffin crossing trial | Hull City Council, MP&I |
Caroline Street | 17 October 2021 | 18 October 2021 | Emergency – gas escape | NGN |
Bellfield Avenue | 20 September 2021 | 18 October 2021 (extended) | Essential repairs, footway and carriageway | YW |
Hawthorne Avenue | 11 October 2021 | 15 October 2021 | New connections | YW |
Hessle Road | 14 October 2021 | 19 October 2021 | Network Connections – lane closure | YW |
Saltshouse Road | Delayed – awaiting new date | Installation of two new pedestrian refuge islands between Dunvegan Road and Clearview Close | Hull City Council. MP&I |