Here is the latest breakdown of scheduled and emergency works taking place across Hull over the next few weeks. All works are subject to change.
For the latest updates:
- Visit Travel Hull: Homepage – Travel Hull
- Follow Travel Hull on X and Facebook
- Check Live Traffic and Travel – Travel Hull before travelling
| Location | Start date | Due date | Summary of works | Utility/HCC |
|---|---|---|---|---|
| Abbey Street | 29-Jul-26 | 04-Aug-26 | Works to excavate and repair sewer putside number 81. Two-way signals in place. | Yorkshire Water |
| Anlaby Road | 10-Aug-26 | 21-Aug-26 | Excavate to install HV ducting on road crossing and HV cable route. Multi-way signals in place. | MUA Elecricity |
| Auckland Avenue | 20-Jul-26 | 21-Aug-26 | Utility works. Multi-way signals in place. | Northern Powergrid |
| Chanterlands Avenue | 03-Aug-26 | 31-Aug-26 | Utility works at the junction of Murryfield Road. Multi-way signals in place. | Northern Powergrid |
| Ennerdale | 02-Mar-26 | 29-Oct-26 | Roundabout improvement works. Lane closure in place. | Hull City Council |
| Falkland Road | 11-May-26 | 17-Sep-26 | Carriageway resurfacing scheme. Phased road closures in place. | Hull City Council |
| Holderness Road | 03-Aug-26 | 04-Aug-26 | Utility works. Multi-way signals in place. | Yorkshire Water |
| Inglemire Lane | 20-Jul-26 | 21-Aug-26 | Utility works. Multi-way signals in place. | Northern Powergrid |
| Lowther Street | 29-Jul-26 | 04-Aug-26 | Excavate and repair cable fault at the junction of Paisley Street. Multi-way signals in place. | Northern Powergrid |
| Marfleet Lane | 26-Aug-26 | 26-Aug-26 | Installation of parallel crossing. Road closure in place. | Hull City Council |
| Marfleet Lane | 23-Jul-26 | 29-Aug-26 | Utility worksfrom number 702 to 732. Two-way signals in place. | Northern Powergrid |
| Spring Bank | 10-Aug-26 | 28-Aug-26 | To build new joint box and lay new duct near the junction of Park Street. Lane closure in place. | BT |
| Stoneferry Road | 27-Jul-26 | 05-Aug-26 | Re-excavate joint bays for DNO HV Connection for stagecoach bus depot, backfill and permanenet reinstatement. Lane closure in place from Withernsea Street to Foster Street. | Advanced Electricity Network |
| Sutton Road | 03-Aug-26 | 14-Aug-26 | Utility works opposite Iroka house. Two-way signals in place. | Yorkshire Water |
| Swanfield Road | 14-Aug-26 | 28-Aug-26 | Utility works from Mirfield Grove to Wakefied Road. Mu;ti-way signals in place. | Northern Powergrid |
| Terry Street | 13-Aug-26 | 13-Aug-26 | Excavation of a trial hole to assess telecoms equiptment at the side of 177 Beverley Road. Two-way signals in place. | 02 |
| Tower Street | 03-Aug-26 | 12-Aug-26 | Utility works. Two-way signals in place. | Northern Powergrid |
| Wawne Road roundabout | 08-May-26 | 06-Aug-26 | Council improvement scheme. Roundabout connecting Bude Road, Wawne Road and Holwell Road Road closure in place. | Hull City Council |
| Wawne Road | 23-Jul-26 | 05-Aug-26 | Utility works. Two-way signals in place. | Northern Gas Networks |
| Wawne Road | 13-Aug-26 | 26-Aug-26 | Telecom works from 19 Wawne Road to the junction of Noddle Hill Way. Multi-way signals in place. | BT |
| Wincolmlee | 13-Jul-26 | 07-Aug-26 | Emergency water leak. Road closure at junction with Air Street. | Yorkshire Water |
| Witham | 03-Aug-26 | 04-Aug-26 | Install washout hydrant to water main near Vault Bar. Lane closure in place. | Yorkshire Water |