Here is the latest breakdown of scheduled and emergency works taking place across Hull over the next few weeks. All works are subject to change.
For the latest updates:
- Visit Travel Hull: Homepage – Travel Hull
- Follow Travel Hull on X and Facebook
- Visit National Highways for more information on planned roadworks, or follow them on X @HighwaysYORKS
- Check one.network before travelling
| Location | Start date | Due date | Summary of works | Utility/HCC |
| A63 improvement scheme – St James Street to Market Place | 01-May-20 | 31-May-26 | Major A63 Improvement scheme – full infrastructure change, operating under a Development Control Order which gives the powers to National Highways to implement this scheme. Lane and road closures until completion of scheme. | National Highways |
| Alfred Gelder Street | 31-Jan-26 | 01-Feb-26 | Section 50 connection for District Heat. Two-way signals at the junction with Ghandi Way. Off-peak working only. | Hull City Council |
| Anlaby Road | 05-Jan-26 | 10-Feb-26 | Replacing gas pipe at the junction of Anlaby Road to outside 700. Road closure in place. | Northern Gas Networks |
| Chapel Lane | 26-Jan-26 | 13-Feb-26 | Mains connection at the junction of High Street. Road closure in place. Phased works, High Street to be open while Chapel Lane is closed. Weekday working only. Site clear at the weekends. | Northern Power Grid |
| Cottingham Road/Hall Road Roundabout | 02-Feb-26 | 13-Feb-26 | Carriageway resurfacing delivered in two phases, maintaining traffic flow between Hall Road and Fairfax Avenue with temporary signals. Throughout the duration of these works, access to Hotham Road North and Cottingham Road on both sides of the roundabout will be closed. | Hull City Council |
| Green Lane | 06-Feb-26 | 13-Feb-26 | Disconnection of supply at the junction of Toogood Street. Multi-way signals in place. | Northern Power Grid |
| High Street | 26-Jan-26 | 13-Feb-26 | Mains connection at the junction of Chapel Lane. Road closure in place. Phased works, Chapel Lane to be open while High Street is closed. Weekday working only. Site clear at the weekends. | Northern Power Grid |
| Humber Dock Street | 03-Feb-25 | 30-Apr-26 | Public realm works, road closure in place. Works are to take place on the public right of way along Humber Dock Street between junctions with Blanket Row and Humber Street. | Hull City Council |
| Main Road | 05-Jan-26 | 13-Feb-26 | Replacing gas pipe outside 9 to 93. Multi-way signals in place. | Northern Gas Networks |
| National Avenue | 15-Jan-26 | 11-Feb-26 | Renew mains cable from the junction with Bontoft Avenue. Multi-way signals in place. | Northern Power Grid |
| Princes Dock Street | 03-Feb-25 | 30-Apr-26 | Works are part of Hull Public Realm development scheme. Road closure in place. | Hull City Council |
| Scale Lane footbridge | 19-Jan-26 | 06-Feb-26 | Investigation works to footbridge. There will be times when the footbridge may have to close to pedestrians and cyclists with a short, signed diversion over the Millenium footbridge. | Hull City Council |