Hull City Council is set to launch its annual surface dressing programme, giving 12 key roads across the city a much-needed upgrade to improve safety and extend their lifespan.
The city-wide programme will begin on Monday 21 July and is scheduled to be completed by Thursday 31 July, weather permitting. No work will take place over the weekend.
This year’s programme focuses on roads that form part of Hull’s major road network and main bus routes, which are showing early signs of wear and deterioration.
Surface dressing is a preventative maintenance treatment that seals the road surface, helping to avoid more serious damage and costly repairs in the future.
By acting now, the council aims to extend the lifespan of these roads, improve quality, and enhance skid resistance – making them safer for all road users.
Preparation works, including patching and crack sealing, have already been carried out where necessary to ensure the roads are ready for treatment.
To keep residents informed, road closure notices have been erected – where needed – and letter drops will be carried out prior to the start of works at each location. In addition, the contractor will distribute leaflets with further details about the works and what residents can expect.


Councillor Mark Ieronimo, portfolio holder for transport and infrastructure, said: “Surface dressing is essential for keeping these roads in the city well-maintained and safe for all road-users.
“We understand that roadworks can be inconvenient, and we’ll do everything we can to minimise disruption.
“Thank you to residents and road users for your patience while we carry out these essential improvements.”
The roads that are included as part of the programme, as well as the proposed dates and traffic management arrangements, are listed below.
Please note, these dates are weather dependent and are subject to change:
Date | Street name | Location | Traffic management | Timings |
---|---|---|---|---|
Monday 21 July | Orchard Park Road | Ellerburn Avenue to Cladshaw | Stop / Go | 9am-4pm |
Monday 21 July | Queens Road | Beverley Road to Princes Avenue | Stop / Go | 6am-8am |
Tuesday 22 July | Bethune Avenue | Anlaby Park Road South to the ERYC boundary | Stop / Go | 9am-4pm |
Wednesday 23 July | Boothferry Road (eastbound and westbound) | Anlaby Park Road north/south junction to the ERYC boundary | Lane closures | 9.30am-3.30pm |
Thursday 24 July | Kingsbury Way | Blackwater Way mini roundabout to Kesteven Way | Stop / Go | 9am-4pm |
Thursday 24 July | Lythe Avenue | Bishop Alcock Road to the ERYC boundary | Stop / Go | 9am-4pm |
Thursday 24 July | Holwell Road | Section over bridge between Sutton Road roundabout and Nidderdale / Barnstaple Road roundabout | Stop / Go | 9.30am-3.30pm |
Monday 28 July | Brighton Street (northbound and southbound) | Witty Street roundabout to the A63 roundabout | Lane closures | 9.30am-3.30pm |
Tuesday 29 July | Willerby Road (eastbound) | ERYC boundary to the County Road junction | Part Lane closure and part road closure with signed diversion | 9.30am-3.30pm |
Tuesday 29 July | Cannon Street | Bridlington Avenue to Lockwood Street | Stop / Go | 9am-4pm |
Wednesday 30 July | James Reckitt Avenue | Chamberlain Road to Gillshill Road | Phased road closures with signed diversions | 9.30am-3.30pm |
Thursday 31 July | Beverley Road (southbound) | Hall road junction to Sutton Road junction. | Lane closures | 9.30am-3.30pm |