Here is the latest breakdown of scheduled and emergency works taking place across Hull over the next few weeks. All works are subject to change.
For the latest updates:
- Visit National Highways for more information on planned roadworks, or follow them on X (formerly Twitter) @HighwaysYORKS
- Follow @hullccnews on X (formerly Twitter)
- Follow the Hull City Council Facebook page
- Check one.network before travelling
A63 improvement scheme – St James Street to Market Place | 01-May-20 | 31-May-26 | Major A63 Improvement scheme – full infrastructure change. Lane and road closures until completion of scheme. | National Highways |
Anlaby Road | 28-Mar-25 | 30-May-25 | Gas works. Bus lane closure from Hull Royal to the junction of Park Street/Icehouse Road. | Northern Gas Networks |
Beverley Road | 17-Mar-25 | 11-Jul-25 | Gas works. Lane closure in place from number 53 to the junction of Margaret Street. | Northern Gas Networks |
Boulevard | 14-Apr-25 | 04-May-25 | Carriageway reconstruction and resurfacing from Hessle Road to Witty Street. Road closure in place. | Hull City Council |
Brighton Street | 02-May-25 | 07-May-25 | Carriageway resurfacing at the Brighton Street, Witty Street, and Freightliner Road roundabout. Road closure in place. | Hull City Council |
Danube Road | 07-Apr-25 | 13-Jun-25 | Installing drainage connections for new Living With Water aquagreen. Also sewer works and the creation of a speed hump. Road closure in place. | Yorkshire Water |
Ennerdale | 06-May-25 | 19-May-25 | Install new cable at the rear of 11-13 Riverview Gardens. Multi-way signals in place. | Northern Powergrid |
Ferensway | 27-Apr-25 | 28-Apr-25 | Repair sewers near 119 Ferensway. Lane closure in place. | Yorkshire Water |
Guildhall Road | 01-May-23 | 31-Oct-25 | Public realm works, including paving, surfacing, drainage, retaining walls and ducting within Queens Gardens and along Guildhall Road, Wilberforce Drive and Queens Dock Avenue. Lane closure on Guildhall Road. | Hull City Council |
Humber Dock Street | 01-Feb-25 | 21-Oct-25 | Public realm works, road closure in place. Works are to take place on the public right of way along Humber Dock Street between junctions with Blanket Row and Humber Street. | Hull City Council |
Icehouse Road | 28-Apr-25 | 28-May-25 | Gas works at the junction of Anlaby Road. Road closure in place. | Northern Gas Networks |
Ilford Road | 04-Dec-24 | 02-May-25 | Constructing new manholes and connecting sewer pipework to allow for the connection of SUDS aqua greens, built off the highway back into the sewer system. Road closure on Ilford Road between Worcester Road and Bristol Road. | Yorkshire Water |
James Reckitt Avenue | 14-Apr-25 | 29-Apr-25 | Telecoms works. Two-way signals in place from 272 James Reckitt Avenue to the junction of Summergangs Road. | Grain |
Margaret Street | 22-Apr-25 | 06-May-25 | Road closure due to works on Beverley Road. | Northern Gas Networks |
Micro-surfacing programme | 06-May-25 | 13-Jun-25 | Various road closures across the city for the annual micro-surfacing programme. | Hull City Council |
Middlesex Road | 24-Mar-25 | 31-Aug-25 | Carriageway and footway refurbishments. Road closure in place. | S278/ Hull City Council |
New Bridge Road | 14-Apr-25 | 29-Apr-25 | Telecoms works. Two-way signals in place. | MS3 |
Park Street | 28-Apr-25 | 28-May-25 | Gas works outside National Tyres and Autocare. Road closure in place. | Northern Gas Networks |
Pennine Way | 28-Apr-25 | 09-May-25 | Telecoms work near 11 Kettlewell Close. Two-way signals in place. | KCOM |
Princes Avenue | 07-Apr-25 | 16-May-25 | Connection only due to works on Queens Road. Two-way signals in place. | Northern Gas Networks Hull City Council |
Queens Dock Avenue | 22-May-23 | 31-Oct-25 | Public realm works, Lane closure in place. | Hull City Council |
Queens Road | 07-Apr-25 | 16-May-25 | Essential gas works and carriageway resurfacing. Road closure at the junction of Queens Road and Princes Avenue. | Northern Gas Networks Hull City Council |
Spring Bank West | 18-May-25 | 18-May-25 | Uplift the Walton Street level crossing for re railing. Hours of work 00:01 – 07:00. | Network Rail |
Spring Bank West | 01-Jun-25 | 01-Jun-25 | Walton Street level crossing uplift for rail works. Hours of works 00.01 – 07.00 | Network Rail |
St Georges Road | 03-May-25 | 03-May-25 | Level crossing test. Multi-way signals in place from one minute past midnight to 5am. | Network Rail |
Wellington Lane | 14-Apr-25 | 02-May-25 | Road closure due to works on Beverley Road. | Northern Gas Networks |