Below is a breakdown of roadworks taking place across Hull over the next few weeks. All works are subject to change. For the latest updates:
- Follow @hullccnews on Twitter
- Follow the Hull City Council Facebook page
- Check one.network before travelling.
A63 improvement scheme - St James Street to Market Place | 01 May 2020 | 01 May 2025 | Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. | National Highways |
A63 improvement scheme - Commercial Road | 26 October 2021 | 30 April 2024 | Enable H&S and safe systems of works for operatives working on the scheme. | National Highways |
Beverley Road - Brunswick Arcade | 04 October 2021 | 01 April 2023 | Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022. | HCC - MP&I |
Beverley Road | 30 May 2022 | 01 June 2022 | Remedial works to lining. Lane closure between Mizzen Road and Sutton Road, Monday to Friday, 7.30pm to 11pm | HCC - MP&I |
Beverley Road | 06 June 2022 | 10 June 2022 | Construction of additional length of off-road cycle track. Lane closure 9.30am - 3.30pm. Mizzen Road to city boundary. | HCC - MP&I |
Calvert Lane | 16 May 2022 | 10 July 2022 | Carriageway resurfacing scheme from approximately 50m north of Boundary Way to Calvert Lane fire station. Road closed. Diversion in place. Access to be maintained at all times. | HCC - MP&I |
Charles Street | 04 April 2022 | 15 June 2022 | Works between Francis Street and Bridlington Avenue, including work in the carriageway and footpath. Removal of existing line markings, installation of new gullies and kerbs to construct off-road cycle track. New surfacing and line markings. Multi-way signals, to be manned at peak times. | HCC - MP&I |
Ferensway | 27 May 2022 | 28 May 2022 | Road coring within existing carriageway at junction with Osborne Street. Multi-way signals. Work to take place overnight from 7pm - 5am. | HCC - MP&I |
Gillshill Road | 24 May 2022 | 07 June 2022 | Works between Sutton House Road and Ings Road junction to establish new gas connection. Two-way signals. | Northern Gas Network |
Great Union Street | 23 May 2022 | 26 June 2022 | Resurfacing / concrete repairs. Full road closure. Access to be maintained at all times for businesses via A63 / Clarence Street. | HCC - MP&I |
Greenwood Avenue | 06 June 2022 | 08 June 2022 | Installation of telecommunications cabinet. Lane closure with multi-way signals from 9.30am - 3.30pm. | HCC - MP&I |
Hawthorne Avenue | 20 June 2022 | 24 June 2022 | Level crossing and track survey. Lane closure with two-way signals from 11pm - 5.30am. | Network Rail |
Hessle Road (12-month Scheme) | 23 August 2021 | 04 September 2022 | Footway reconstruction. | HCC - MP&I |
High Street | 16 May 2022 | 18 July 2022 | Laying ducting, kerbs/ edgings, installation of cobbled paving under Myton Bridge. Multi-way signals. | National Highways |
Holderness Road (Victor St to Southcoates) (PHASES 1-8) | 04 January 2022 | 11 September 2022 | Full footway reconstruction scheme. | MP&I - Highways Strategy & Design |
Ings Road | 09 May 2022 | 01 June 2022 | Lane closure in place entrance between 9am and 3pm from the junction of Eglington Avenue to Crooked Billet car park entrance. | Northern Gas Network |
National Avenue | 18 May 2022 | 28 May 2022 | New power supply outside Caradon Heating. Two-way signals. | Northern Powergrid |
Park Street | 06 June 2022 | 17 June 2022 | Replacement of gas main. Road closure. Westbound road closure (Caughey Street to Spring Bank). No access from Spring Bank. Access from Park Street to Spring Bank still available. | Northern Gas Network |
Priory Way | 01 April 2022 | 31 March 2023 | Major improvement scheme. | HCC - MP&I |
Stoneferry Rd Scheme - Woodhall Street to Lorraine Street | 01 April 2021 | 01 July 2022 | Major Improvement Scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall Street junction are now completed. | HCC - MP&I |
Stoneferry Rd Scheme - Chamberlain Road to Bandstand Roundabout | 23 April 2021 | 01 July 2022 | Major improvement scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall Street junction are now completed. | HCC - MP&I / Colas |
Stoneferry Rd Scheme - Leads Road | 25 April 2022 | 29 July 2022 | Renew footpaths and kerbs. Leads Road closed westbound between Rotterdam Road and Bandstand Roundabout during works. | HCC - MP&I COLAS |
Stoneferry Rd Scheme - Leads Road | 29 July 2022 | 01 August 2022 | Carriageway resurfacing. Leads Road closed in both directions between Rotterdam Road and Bandstand Roundabout from 7pm on Friday 29 July to 6am on Monday August 1. | HCC - MP&I COLAS |
Stoneferry Rd Scheme - Sutton Road | 03 May 2022 | 01 July 2022 | Reconstruction of the new junction under temporary traffic lights to enable removal of the existing permanent traffic signals. Multi-way signals to run in phases to help minimise disruption. Leads Road / Sutton Road junction. | HCC - MP&I |