It was announced this week that essential road repairs will begin on Calvert Lane later this month.
The work is due to start on Monday 16 May and is expected to last for eight weeks.
Below is a breakdown of roadworks taking place across Hull over the next few weeks. All works are subject to change. For the latest updates:
- Follow @hullccnews on Twitter
- Follow the Hull City Council Facebook page
- Check one.network before travelling.
A63 improvement scheme - St James Street to Market Place | 01 May 2020 | 01 May 2025 | Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. | National Highways |
A63 improvement scheme - Commercial Road | 26 October 2021 | 30 April 2024 | Enable H&S and safe systems of works for operatives working on the scheme. | National Highways |
Beverley Road | 07 March 2022 | 06 May 2022 | Gas Main replacement scheme. Inbound from city Boundary to Mizzen Road. Lane closure. | Northern Gas Networks |
Beverley Road - Brunswick Arcade | 04 October 2021 | 01 September 2022 | Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022. | HCC - MP&I |
Beverley Road/Fountain Road junction | 09 May 2022 | 16 May 2022 | Work to install delineator blocks. Two nights with temporary three-way signals, followed by four days with cycle track and part footpath closure, followed by two nights under three-way signals. Multi-way lights to be used only between 7pm and 11pm. | MP&I ARB (PM) LTD |
Bishop Lane | 16 May 2022 | 19 May 2022 | Install new water supply connection. Full road closure. Local diversion in place. | Yorkshire Water |
Calvert Lane | 16 May 2022 | 10 July 2022 | Carriageway resurfacing scheme from approximately 50m north of Boundary Way to Calvert Lane fire station. Road closed. Diversion in place. Access to be maintained at all times. | HCC - MP&I |
Carr Lane (About Us event) | 30 April 2022 | 06 May 2022 | Carr Lane closed from junction with Chariot Street to junction with Queens Dock Avenue, 8pm-11.30pm daily. Diversion in place. | About Us event |
Charles Street | 04 April 2022 | 20 May 2022 | Works between Francis Street and Bridlington Avenue, including work in the carriageway and footpath. Removal of existing line markings, installation of new gullies and kerbs to construct off-road cycle track. New surfacing and line markings. Multi-way signals, to be manned at peak times. | HCC - MP&I |
Great Union Street | 23 May 2022 | 26 June 2022 | Resurfacing / concrete repairs. Full road closure. Access to be maintained at all times for businesses via A63 / Clarence Street. | HCC - MP&I |
Hessle Road (12-month Scheme) | 23 August 2021 | 04 September 2022 | Footway reconstruction. | HCC - MP&I |
High Street | 11 May 2022 | 12 May 2022 | Re-lay kerbs. Stop & Go signs. Work between 7.30am and 3.30pm. | MP&I - ST GROUP LTD |
Holderness Road (Victor St to Southcoates) (PHASES 1-8) | 04 January 2022 | 11 September 2022 | Full footway reconstruction scheme. | MP&I - Highways Strategy & Design |
Holwell Road | 11 May 2022 | 11 May 2022 | Telecoms maintenance. Two-way signals. Works between 9.30am and 3.30pm. | T-Mobile |
Hopewell Road | 14 March 2022 | 05 May 2022 | Concrete repairs and carriageway resurfacing. Road closure from Slaveley Road junction to Taylor Avenue. | HCC - MP&I |
Howdale Road - Phase 2 | 16 May 2022 | 27 May 2022 | Date changed. Trench repair on 2nd half of carriageway. Multi-way signals. Junction of Oaktree Drive. 8am start on Sunday. Traffic management to be removed once concrete has cured. | Streetscene Highway Operations |
Ings Road | 09 May 2022 | 19 May 2022 | Lane closure in place entrance between 9am and 3pm from the junction of Eglington Avenue to Crooked Billet car park entrance. | Northern Gas Network |
Mount Pleasant | 07 May 2022 | 09 May 2022 | Installation of duct crossing on Mount Pleasant between Wilmington waste disposal site and James Reckitt Avenue junction. Traffic signals from 7.30am on Saturday May 7, to be removed before 6am on Monday May 9. | HCC - Colas |
National Avenue | 18 May 2022 | 28 May 2022 | New power supply outside Caradon Heating. Two-way signals. | Northern Powergrid |
Paragon Street - About Us Event | 23 April 2022 | 09 May 2022 | Paragon Street from junction with Chariot Street to eastern end of road. | About Us Event |
Park Street | 06 June 2022 | 17 June 2022 | Replacement of gas main. Road closure. Westbound road closure (Caughey Street to Spring Bank). No access from Spring Bank. Access from Park Street to Spring Bank still available. | Northern Gas Network |
Princes Avenue | 25 May 2022 | 27 May 2022 | Surfacing and line marking. Two-way signals in place 24 hours a day. | HCC - MP&I |
Priory Way | 01 April 2022 | 31 March 2023 | Major improvement scheme. | HCC - MP&I |
Stoneferry Rd Scheme - Woodhall Street to Lorraine Street | 01 April 2021 | 01 August 2022 | Major Improvement Scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall Street junction are now completed. | HCC - MP&I |
Stoneferry Rd Scheme - Chamberlain Road to Bandstand Roundabout | 23 April 2021 | 01 August 2022 | Major improvement scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall Street junction are now completed. | HCC - MP&I / Colas |
Stoneferry Rd Scheme - Leads Road | 25 April 2022 | 29 July 2022 | Renew footpaths and kerbs. Leads Road closed westbound between Rotterdam Road and Bandstand Roundabout during works. | HCC - MP&I / Colas |
Stoneferry Rd Scheme - Leads Road | 29 July 2022 | 01 August 2022 | Carriageway resurfacing. Leads Road closed in both directions between Rotterdam Road and Bandstand Roundabout from 7pm on Friday 29 July to 6am on Monday August 1. | HCC - MP&I / Colas |
Stoneferry Rd Scheme - Sutton Road | 03 May 2022 | 01 July 2022 | Reconstruction of the new junction under temporary traffic lights to enable removal of the existing permanent traffic signals. Multi-way signals to run in phases to help minimise disruption. Leads Road / Sutton Road junction. | HCC - MP&I |