Roadworks are to take place in Hull.
Essential repairs to Willerby Road will be carried out later this year.

Weekly roadworks update – March 18

After significant rainfall affected work on the Stoneferry improvement scheme on Wednesday night, resurfacing in West Carr Lane will now require an extra night to be completed.

This will also have knock-on effect on previously announced work on Holwell Road/Sutton Road.

Below is a breakdown of roadworks taking place across Hull over the next few weeks. All works are subject to change, so motorists are also advised to check one.network for the latest updates.

LocationStart DateDue DateReasonUtility/HCC Name
26th Avenue / Greenwood Ave28-Mar-2231-Mar-22Telecoms pole installation. Junction of Greenwood Avenue (footway). Multi-way Signals. Activities to take place between 7pm-11pm on day 1, then 9.30am-3.30pm on day 2. Day 3 and 4, no carriageway incursion. T-Mobile Ltd - Ericsson
A63 improvement scheme - St James Street to Market Place01 May 202001 May 2025Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre.National Highways
A63 improvement scheme - Brighton Street to Roger Millward Way07 March 202225 March 2022Road closure eastbound from Brighton Street to Roger Millward Way and westbound from Roger Millward Way to Daltry Street. Weeknights from 8pm - 6am.40 Seven Ltd
A63 improvement scheme - Commercial Road26 October 202130 April 2022Enable H&S and safe systems of works for operatives working on the scheme.National Highways
Bellfield Avenue10 January 202206 April 2022Multi-way signals at the junction with Savoy Road. Manned between traffic sensitive times.HCC - MP&I
Bellfield Avenue06 March 202208 April 2022Road closure for carriageway resurfacing. Works to take place between 7pm - 6am. Local diversion in place.Section 278
Beverley Road07 March 202222 April 2022Gas Main replacement scheme. Inbound from city Boundary to Mizzen Road. Lane ClosureNorthern Gas Networks
Beverley Road - Brunswick Arcade04 October 202101 September 2022Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022.HCC - MP&I
Hall Road15 March 202225 March 2022Cherry picker to access telecoms mast for testing and maintenance works from 9.30am-3.30pm approx 100m west of Thorpepark Road. Two-way signals.O2 (GS Hall)
Hessle Road (12-month Scheme)23 August 202104 September 2022Footway reconstruction.HCC - MP&I
High Street18-Mar-2219-Mar-22The Awakenings event. Road closure between Liberty Lane and Gandhi Way, 6pm-midnightFreedom Festival
Holderness Road (Victor St to Southcoates) (PHASES 1-8)04 January 202211 September 2022Full footway reconstruction scheme.MP&I - Highways Strategy & Design
Holwell Road24-Mar-2225-Mar-22Approx 25m south of Goodhart road. Minor, non-excavation works. Two-way traffic lights in place 9.30am-3.30pm.O2 (GS Hall)
Hopewell Road14 March 202224 April 2022Concrete repairs and carriageway resurfacing. Road closure from Slaveley Road junction to Taylor Avenue.HCC - MP&I
Humber Street07 February 202219 March 2022Installation of bollards. Works span width of footway and carriageway outside Dinostar. Work will be done in sections to maintain pedestrian walkway.HCC - MP&I
Lowgate Footway Scheme - West / East Footway22 October 202116 April 2022Footway repair scheme. Scheme delayed due to signal failure on A63. Northbound closure. Current traffic management set-up to remain in place for duration of scheme.HCC - MP&I
Queens Dock Avenue18-Mar-2219-Mar-22The Awakenings event. Road Closure between Carr Lane and George Street. 6pm - 11pm.Freedom Festival
Rawlings Way04-Apr-2204-Apr-22Cutting of new loops. Multi-way signals. Working hours 7pm - 11pmStreetScene - Traffic Signals
Stoneferry Rd Scheme - Woodhall Street to Lorraine Street01 April 202101 April 2022Major Improvement Scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed.HCC - MP&I
Stoneferry Rd Scheme - Chamberlain Road to Bandstand Roundabout23 April 202101 April 2022Major improvement scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed.HCC - MP&I / Colas
Stoneferry Rd Scheme - West Carr Lane15 March 202219 March 2022Surfacing to West Carr Lane. Road closure from NR Burnett entrance to junction with Stoneferry Road / Holwell Road Closures from 7pm to 6am, Mon to Fri nights. HCC - MP&I / Colas
Stoneferry Rd Scheme - Sutton Road21 March 202224 March 2022Surfacing of Sutton Road, Road closure eastbound from junction with Holwell Roundabout for approx 120m.HCC - MP&I / Colas
Stoneferry Rd Scheme - Holwell Road21 March 202224 March 2022Surfacing of Holwell Road. Road closure northbound from junction with Sutton Road.HCC - MP&I / Colas
Wincolmlee (Phase 2)16 March 202228 March 2022Road closure for new connection and cable upgrades. Works delayed due to gas leak, completion date could change.Northern Powergrid
North End Shipyard