Essential work to improve Hull’s roads will continue next week.
Work to repair poor road surfacing in Priory Road will start on Monday 2 August.
The improvement works will be carried out in two phases over the summer holiday period to ensure there is minimum disruption to residents and motorists.
Councillor Dean Kirk, portfolio holder for transportation, roads and highways, said: “Schools have broken up for summer holidays, and we know that this means traffic will be lighter on the roads.
“We understand that roadworks can be frustrating for motorists, however these works are essential if we are to improve the city’s infrastructure for better and safer journeys in the future. We apologise for any inconvenience to drivers in the meantime.
“A letter drop has been issued to residents and businesses in the area, giving them the opportunity to inform the team of any special requirements so the repair work can be accommodated accordingly.
“We are grateful to residents of Priory Road and, while we understand the inconvenience, their cooperation will help to ensure that the work is completed without delay and that these essential works are completed as quickly as possible.”
Alongside this, work to improve road surfacing and reduce the number of potholes on Hull’s roads will begin next week.
A total of 64,096 square-meters of road space will be resurfaced which will require some lane closures, road closures and night working.
Advance warning signs will be in place and residents in the affected areas will be informed with letter drops.
Councillor Kirk said: “We’re also encouraging motorists to have their say on traffic and transport issues as part of our latest survey.”
The survey can be accessed on the Hull City Council website.
Motorists are advised to keep up-to-date with Stoneferry Corridor works download the Hello Travaux app on the App Store on Google Play.
Below is a breakdown of the planned roadworks taking place in Hull:
Location | Start date | Completion date | Details of work | Organisation | Current status |
A63 Castle Street – From St James Street to Market Place.
|
May 2020 | May 2025 | Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGV’s in city centre | Highways England | On track |
Stoneferry Corridor – Woodhall Street – Lorraine Avenue | Commenced | 28 May 2022 | Installation of the Stoneferry Road Corridor works | Hull City Council | On track |
Stoneferry Corridor – Chamberlain Road to Bandstand Roundabout | 23 April 2021 | 25 June 2022 | Installation of the Stoneferry Road Corridor works | Hull City Council | On track |
Stoneferry Corridor – Sutton Road – Leads Road | June 2021 | December 2022 | Installation of the Stoneferry Road Corridor works | Hull City Council | On track |
Wiltshire Road | 14 June 2021 | 22 August 2021 | Excavate existing concrete carriageway and carry out any required repairs
|
Hull City Council | On track |
Humber Street & High Street | 21 June 2021 | 7 Oct 2021 | Reconstruction of footpaths and road surface | Hull City Council | On track |
Dunvegan Road | 28 June 2021 | 15 August 2021 | Essential footway repairs | Hull City Council | On track |
Holderness Road (Ings to Diadem) | 19 July | 20 August 2021 | Installation of cycle lane | Hull City Council | Planned |
Spring Bank West | 19 July 2021 | 24 September 2021 | Essential gas works in footways | Northern Gas Networks | On track |
Wincolmlee | 26 July 2021 | 4 August 2021 | Essential works – new connection | Northern Powergrid | Extended by five days |
High Street | 2 August 2021 | 6 August 2021 | Road closure will be in place | Yorkshire Water | Planned |
Priory Road | 2 August 2021 | 27 September 2021 | Carriageway & footway re-construction & bus lanes/ parking bays | Hull City Council | Planned |
Commercial Road | 2 August 2021 | 25 October 2021 | A63 improvement scheme, no left turn from commercial road onto A63. Access via Daltry Street. | Highways England | Planned |
Preston Road | 5 August 2021 | 6 August 2021 | Road resurfacing – overnight closure
|
Hull City Council | Planned |
Hedon Road
|
10 August 2021 | 11 August 2021 | Road resurfacing – overnight closure | Hull City Council | Planned |
Brunswick Arcade (Beverley Road) | 16 August 2021 | November 2022 | Lane closures from October 2021 onwards | Hull City Council | Planned |
Greenwood Avenue | 16 August 2021 | 18 August 2021 | Mobile mast works – traffic management | T-Mobile | Planned |
South Street – Carr Lane, Osborne Street – Anne Street | 23 August 2021 | 25 August 2021 | Resurfacing scheme with overnight works | Hull City Council | Planned |
Sutton Road flyover | 25 August 2021 | 26 August 2021 | Essential bridge maintenance. Evening road closure (7pm-6am) | Hull City Council | Planned |
Beverley Road – full length | September 2021 | December 2021 | Installation of cycle lanes | Hull City Council | Planned |
Holderness Road | September 2021 | September 2022 | Reconstruction of pavements | Hull City Council | Planned |
Hessle Road | September 2021 | September 2022 | Reconstruction of pavements | Hull City Council | Planned |
Lowgate (outside Guildhall) | September 2021 | September 2021 | Crane required to access the clock tower – diversion routes in place | Hull City Council | Planned |
Queen Street | 20 September 2021 | 27 September 2021 | Resurfacing scheme | Hull City Council | Planned |
Bowl Alley Lane | 20 September 2021 | 29 October 2021 | Pavement improvements – road closure | Hull City Council | Planned |
Inglemire Lane & Hall Road | 27 September 2021 | 10 October 2021 | Road resurfacing – temp traffic lights | Hull City Council | Planned |
Priory Way | October 2021 | August 2022 | Major widening and construction of three signalised junctions | Hull City Council | Planned |
Air Street | 4 October 2021 | 29 October 2021 | Essential gas works | Northern Gas Networks | Planned |
Silver Street | 1 November 2021 | 30 November 2021 | Installing automatic bollards | Hull City Council | Planned |