Roadworks sign
A number of road closures will be in place for Remembrance Sunday.

Weekly roadworks update – October 29

This week, it was announced that overnight resurfacing works would be taking place from Monday November 8 as part of the Stoneferry improvement scheme.

The work, which is expected to last about a week, will be carried out from 7pm to 6am, Monday to Friday (including Saturday morning).

During the work, Stoneferry Road (southbound) will be closed from Ferry Lane Roundabout to Chamberlain Roundabout. This will include the Lorraine Street junction.

Councillor Dean Kirk, portfolio holder for transportation, roads and highways said: “These closures will be overnight in order to minimise disruption and ensure this stage of the works can be completed as quickly and efficiently as possible.”

Read more here.

A breakdown of planned works taking place across Hull has been detailed below:

Location Start Date Due Date Reason Utility/HCC Name
A63 improvement scheme – Commercial Road 26 October 2021 30 April 2022 Enable H&S and safe systems of works for operatives working on the scheme National Highways
A63 Castle Street scheme –  St James Street to  Market place 01 May 2020 01 May 2025 Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. National Highways
Beverley Road  (split into phases) 23 August 2021 03 December 2021 Implementation of cycle scheme. Queens Road/ Beverley Road and Cottingham Rd/Clough Road junctions HCC – MP&I
Beverley Road Inbound (Phase 1) 31 August 2021 12 November 2021 Construction of cycle way. City Centre boundary to Mizzen Road.  Works mainly in the verge with kerb works in channel. Lane Closure 24/7 HCC – MP&I
Beverley Road 14 October 2021 19 November 2021 Construction of off-line cycle track. Hall Road to City Boundary outbound. Lane closure throughout duration of works. HCC – MP&I
Beverley Road 22 October 2021 03 December 2021 Implementation of cycle scheme. Mizzen road to Hall Road Inbound. 9.30am to 3.30pm lane closures HCC – MP&I
Beverley Road 18 October 2021 25 October 2021 New gas connection. Closure of bus lane Northern Gas Network
Beverley Road 08 November 2021 19 November 2021 Variable messaging sign installation. Beverley Road northbound footway, adjacent to Eldon Grove. Lane 1 closure required adjacent to work area. HCC – MP&I
Bond Street / Albion Street 08 November 2021 22 November 2021 BHS, Survey works. 8pm – 6am signals at junction of Bond / George Street & Bond / Albion Street. Various lane closures HCC – MP&I
Bowlalley Lane 18 October 2021 17 December 2021 Footway Scheme. Extended to include carriageway. Road closure HCC – MP&I
Calvert Lane 01 November 2021 10 November 2021 Final resurfacing works. HCC – Streetscene Signals
Freetown Way 08 November 2021 19 November 2021 Installation of variable messaging sign in central reservation on Freetown Way, from Wright Street to Bridlington Ave. o2
Hall Road 11 November 2021 11 November 2021 Installation of telecoms mast off junction with access road to superstore. 9.30am – 3.30pm. Works expected to take no longer than three hours. HCC – MP&I
Hessle Road (12 month Scheme) 23 August 2021 04 September 2022 Footway scheme, reconstructions HCC – MP&I
Holderness Road  (Victor St to Southcoates) (PHASES 1-8) 27 September 2021 01 November 2021 Full footway reconstruction scheme. HCC – MP&I
Lowgate Footway Scheme – Market Place 20 September 2021 22 December 2021 Footway repair scheme. From A63 up towards North Church site west footway. Some parking bays removed for walkway HCC – MP&I
Lowgate Footway Scheme – Market Place 22 October 2021 22 December 2021 Footway repair scheme. East footway – no carriageway incursion. Except on occasions, parking bays removed to provide walkway HCC – MP&I
Lowgate – Footway West Side 01 November 2021 10 January 2022 Footway repair Scheme. Alfred Gelder to North Church Side. One-way closure to northbound lane for duration of works. HCC-MP&I
Saltshouse Road 28 October 2021 12 January 2022 Installation of two new pedestrian refuge islands between Dunvegan Road and Clear View Close Northern Gas Network
Spring Bank West 25 October 2021 03 December 2021 Upgrading network. Opposite Albert Ave to Tile Giant (footway, carriageway) HCC – Streetscene Signals
Spring Bank West 08 November 2021 19 November 2021 Variable messaging sign installation. Spring Bank West, westbound verge. Lane 1 closure and relocation of bus stop required off peak. HCC – MP&I  COLAS
Stoneferry Rd Scheme – Chamberlain Road to Bandstand Roundabout 23 April 2021 25 June 2022 Major improvement scheme commissioned by HCC  – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed HCC – MP&I  COLAS
Stoneferry Rd Scheme – Woodhall Street to Lorraine Ave 01 April 2021 28 May 2022 Major Improvement Scheme commissioned by HCC  – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed HCC – MP&I
Stoneferry Rd Scheme – Woodhall Street to Chamberlain Road 18 October 2021 30 October 2021 Relocation of gullies. Road closure between Woodhall street and Chamberlain Road. 7pm to 6am. HCC – MP&I  COLAS
Stoneferry Rd Scheme – Ferry Lane 01 November 2021 06 November 2021 Road surfacing. Ferry Lane – eastbound only from Ferry Lane bridge to the roundabout with Stoneferry Road HCC – MP&I  COLAS
Stoneferry Rd Scheme – Ferry Lane Roundabout to Bandstand Roundabout. 01 November 2021 06 November 2021 Road surfacing. Stoneferry Road – northbound only between Ferry Lane roundabout and Bandstand roundabout. HCC – MP&I  COLAS
Stoneferry Rd Scheme – Ferry Lane 15 November 2021 20 November 2021 Road Surfacing. Ferry Lane westbound from Stoneferry Road Roundabout to Ferry Lane Bridge (Carriageway) HCC – MP&I  COLAS
Stoneferry Rd Scheme – Ferry Lane roundabout to Chamberlain Road roundabout 08 November 2021 13 November 2021 Stoneferry Corridor southbound only from Ferry Lane Roundabout to Chamberlain Roundabout for a distance of 0.2 miles from Monday 7pm to Saturday 6am. HCC – MP&I  COLAS
A stylised photo shows Hull's Guildhall, where the council is based, under a wintery blue sky
Councillor Daren Hale, Leader of Hull City Council.