Below is a breakdown of roadworks taking place across Hull over the next few weeks. All works are subject to change. For the latest updates:
- Follow @hullccnews on Twitter
- Follow the Hull City Council Facebook page
- Check one.network before travelling.
A63 improvement scheme - St James Street to Market Place | 01 May 2020 | 01 May 2025 | Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. | National Highways |
A63 improvement scheme - Commercial Road | 26 October 2021 | 30 April 2022 | Enable H&S and safe systems of works for operatives working on the scheme. | National Highways |
Beverley Road | 07 March 2022 | 6 May 2022 | Gas Main replacement scheme. Inbound from city Boundary to Mizzen Road. Lane Closure | Northern Gas Networks |
Beverley Road - Brunswick Arcade | 04 October 2021 | 01 September 2022 | Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022. | HCC - MP&I |
Bishop Lane | 16 May 2022 | 19 May 2022 | Install new water supply connection. Full road closure. Local diversion in place. | Yorkshire Water |
Carr Lane (About Us event) | 30 April 2022 | 06 May 2022 | Carr Lane closed from junction with Chariot Street to junction with Queens Dock Avenue, 8pm-11.30pm daily. Diversion in place. | About Us event |
Charles Street | 04 April 2022 | 20 May 2022 | Works between Francis Street and Bridlington Avenue, including work in the carriageway and footpath. Removal of existing line markings, installation of new gullies and kerbs to construct off-road cycle track. New surfacing and line markings. Multi-way signals, to be manned at peak times. | HCC - MP&I |
Great Union Street | 23 May 2022 | 26 June 2022 | Resurfacing / concrete repairs. Full road closure. Access to be maintained at all times for businesses via A63 / Clarence Street. | HCC - MP&I |
Hessle Road (12-month Scheme) | 23 August 2021 | 04 September 2022 | Footway reconstruction. | HCC - MP&I |
Holderness Road (Victor St to Southcoates) (PHASES 1-8) | 04 January 2022 | 11 September 2022 | Full footway reconstruction scheme. | MP&I - Highways Strategy & Design |
Hopewell Road | 14 March 2022 | 5 May 2022 | Concrete repairs and carriageway resurfacing. Road closure from Slaveley Road junction to Taylor Avenue. | HCC - MP&I |
Howdale Road - Phase 2 | 26 April 2022 | 04 May 2022 | Trench repair on 2nd half of carriageway. Multi-way signals. Junction of Oaktree Drive. 8am start on Sunday. Traffic management to be removed once concrete has cured. | Streetscene Highway Operations |
Ings Road | 09 May 2022 | 19 May 2022 | Lane closure in place entrance between 9am and 3pm from the junction of Eglington Avenue to Crooked Billet car park entrance. | Northern Gas Network |
Paragon Street - About Us Event | 23 April 2022 | 09 May 2022 | Paragon Street – from junction with Chariot Street to eastern end of road. | About Us Event |
Priory Way | 01 April 2022 | 31 March 2023 | Major improvement scheme. | HCC - MP&I |
Stoneferry Rd Scheme - Woodhall Street to Lorraine Street | 01 April 2021 | 01 July 2022 | Major Improvement Scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed. | HCC - MP&I |
Stoneferry Rd Scheme - Chamberlain Road to Bandstand Roundabout | 23 April 2021 | 01 July 2022 | Major improvement scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed. | HCC - MP&I / Colas |
Stoneferry Rd Scheme - Leads Road | 25 April 2022 | 29 July 2022 | Renew footpaths and kerbs. Leads Road closed westbound between Rotterdam Road and Bandstand Roundabout during works. | HCC - MP&I COLAS |
Stoneferry Rd Scheme - Leads Road | 29 July 2022 | 01 August 2022 | Carriageway resurfacing. Leads Road closed in both directions between Rotterdam Road and Bandstand Roundabout from 7pm on Friday 29 July to 6am on Monday August 1. | HCC - MP&I COLAS |
Stoneferry Rd Scheme - Sutton Road | 03 May 2022 | 01 July 2022 | Reconstruction of the new junction under temporary traffic lights to enable removal of the existing permanent traffic signals. Multi-way signals to run in phases to help minimise disruption. Leads Road / Sutton Road junction. | HCC - MP&I |