Roadworks sign

Weekly roadworks update – October 22

This week it was announced that essential overnight resurfacing works would be taking place from Monday November 1 in the latest phase of the multi-million-pound Stoneferry improvement scheme.

The work is expected to last about a week and will be undertaken overnight in order to minimise disruption. The works will be carried out between 7pm and 6am, Monday to Friday.

The carriageway will be closed on Ferry Lane from the River Hull bridge (eastbound) to Ferry Lane roundabout, and on Stoneferry Road (northbound) from Ferry Lane roundabout, past Ann Watson Street, to Bandstand roundabout.

Councillor Dean Kirk, portfolio holder for transportation, roads and highways said: “With the Stoneferry improvement scheme, we are improving access and use for thousands of residents and businesses in the area.”

Read more here

Location Start Date Due Date Reason Utility/HCC Name
A63 improvement scheme – Commercial Road 02 August 2021 25 October 2021 Closure for duration of scheme.  No left turn from Commercial Road on to the A63. Access via Daltry Street National Highways
A63 improvement scheme – Commercial Road 26 October 2021 30 April 2022 Enable H&S and safe systems of works for operatives working on the scheme National Highways
A63 Castle Street scheme –  St James Street to  Market place 01 May 2020 01 May 2025 Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. National Highways
Bellfield Ave 20 September 2021 27 October 2021 Essential Repairs. Extended. Footway and carriageway Yorkshire Water
Beverley Road  (split into phases) 23 August 2021 03 December 2021 Implementation of cycle scheme. Queens Road/ Beverley Road and Cottingham Rd/Clough Road junctions HCC – MP&I
Beverley Road Inbound (Phase 1) 31 August 2021 12 November 2021 Construction of cycle way. City Centre boundary to Mizzen Road.  Works mainly in the verge with kerb works in channel. Lane Closure 24/7 HCC – MP&I
Beverley Road 14 October 2021 19 November 2021 Construction of off-line cycle track. Hall Road to City Boundary outbound. Lane closure throughout duration of works. HCC – MP&I
Beverley Road 22 October 2021 03 December 2021 Implementation of cycle scheme. Mizzen road to Hall Road Inbound. 9.30am to 3.30pm lane closures HCC – MP&I
Beverley Road 18 October 2021 25 October 2021 New gas connection. Closure of bus lane Northern Gas Network
Bond Street / Albion Street 08 November 2021 22 November 2021 BHS, Survey works. 8pm – 6am signals at junction of Bond / George Street & Bond / Albion Street. Various lane closures HCC – MP&I
Bowlalley Lane 18 October 2021 17 December 2021 Footway Scheme. Extended to include carriageway. Road closure HCC – MP&I
Calvert Lane 25 October 2021 29 October 2021 Permit submitted by YW to enable the connections to new buildings Yorkshire Water
Calvert Lane 01 November 2021 10 November 2021 Final resurfacing works. HCC – MP&I
Hawthorne Ave 18 October 2021 27 October 2021 Pot Hole repairs. HCC – Streetscene
Hessle Road (12 month Scheme) 23 August 2021 04 September 2022 Footway scheme, reconstructions. HCC – MP&I
High Street 18 October 2021 25 October 2021 New connection outside 157. Working in collaboration with Yorkshire Water. Norther Power Grid
Holderness Road  (Victor St to Southcoates) (PHASES 1-8) 27 September 2021 01 November 2021 Full footway reconstruction scheme. HCC – MP&I
Inglemire Lane / Greenwood Avenue Junction 01 November 2021 05 November 2021 Mast installation. T-Mobile
Lowgate – Footway West Side 01 November 2021 10 January 2022 Footway repair Scheme. Alfred Gelder to North Church Side. Road Closures for full duration. 7.30pm to 6.00am – Monday to Saturday. HCC – MP&I
Lowgate Footway Scheme – Market Place 20 September 2021 22 December 2021 Footway repair scheme. From A63 up towards North Church site west footway. No Carriageway incursions, except some parking bays removed for walkway. HCC – MP&I
Lowgate Footway Scheme – Market Place 22 October 2021 22 December 2021 Footway repair scheme. East footway – no carriageway incursion. Except on occasions, parking bays removed to provide walkway. HCC – MP&I
New Bridge Road 26 October 2021 26 October 2021 Inspection of rail over road bridge via ladder. Hours of works 9am – 5pm.  Traffic control (multi-way signals). NETWORK RAIL
Saltshouse Road 28 October 2021 12 January 2022 Installation of two new pedestrian refuge islands between Dunvegan Road and Clear View Close. HCC-MP&I
Spring Bank West 25 October 2021 03 December 2021 Upgrading network. Opposite Albert Ave to Tile Giant (footway, carriageway). Northern Gas Network
Stoneferry Rd Scheme – Woodhall to Chamberlain Road 18 October 2021 29 October 2021 Woodhall Street to Chamberlain Road. Carriageway resurfacing works. Road to be closed between 7pm and 6am. Traffic diversions in place. HCC – MP&I  COLAS
Stoneferry Rd Scheme – Chamberlain Road to Bandstand Roundabout 23 April 2021 25 June 2022 Major improvement scheme commissioned by HCC  – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed. HCC – MP&I  COLAS
Stoneferry Rd Scheme – Woodhall Street to Lorraine Ave 01 April 2021 28 May 2022 Major Improvement Scheme commissioned by HCC  – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed. HCC – MP&I  COLAS
Stoneferry Rd Scheme – Woodhall Street to Chamberlain Road 18 October 2021 30 October 2021 Relocation of gullies. Road closure between Woodhall street and Chamberlain Road. 7pm to 6am. HCC – MP&I
Stoneferry Rd Scheme 01 November 2021 06 November 2021 Road surfacing. Ferry Lane – eastbound only from Ferry Lane bridge to the roundabout with Stoneferry Road. HCC – MP&I  COLAS
Stoneferry Rd Scheme 01 November 2021 06 November 2021 Road surfacing. Stoneferry Road – northbound only between Ferry Lane roundabout and Bandstand roundabout. HCC – MP&I  COLAS
Stoneferry Rd Scheme 08 November 2021 13 November 2021 Stoneferry Road from Ferry Lane roundabout to Chamberlain Road roundabout (Carriageway). Stoneferry Corridor southbound only from Ferry Lane Roundabout to Chamberlain Roundabout for a distance of 0.2 miles from Monday 7pm to Saturday 6am. HCC – MP&I  COLAS
Stoneferry Rd Scheme 26 November 2021 29 November 2021 Bandstand Roundabout (junction of West Carr Lane, Leads Road, Holwell Road and Stoneferry Road). Work period: Friday 7pm to Monday 6am. HCC – MP&I  COLAS
Stoneferry Rd Scheme 03 December 2021 06 December 2021 Bandstand Roundabout  – as above. HCC – MP&I  COLAS
Wawne Road 25 October 2021 27 October 2021 Carriageway reconstruction at Cumbrian Way Roundabout – overnight road closure 7pm to 6.30am. HCC – MP&I
Wawne Road 25 October 2021 29 October 2021 Overnight resurfacing of roundabout at junction with Cumbrian Way. HCC – MP&I
Delegates watch the “Eyes on the Humber” film during The Waterline Summit launch event.