Beverley Road has been restored to two lanes inbound outside Brunswick Arcade.

Weekly roadworks update – April 22

Major regeneration works at Brunswick Arcade are ahead of schedule.

The protective hoardings and traffic cones on the short stretch of Beverley Road between Norfolk Street and Trafalgar Street have been moved back towards the kerb, allowing the road to return to two lanes southbound. There remains only one lane northbound at this stage.

Below is a breakdown of roadworks taking place across Hull over the next few weeks. All works are subject to change. For the latest updates:

LocationStart dateDue dateSummary of worksUtility/HCC name
A63 improvement scheme - St James Street to Market Place01 May 202001 May 2025Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre.National Highways
A63 improvement scheme - Commercial Road26 October 202130 April 2022Enable H&S and safe systems of works for operatives working on the scheme.National Highways
Beverley Road07 March 202227 April 2022Gas Main replacement scheme. Inbound from city Boundary to Mizzen Road. Lane ClosureNorthern Gas Networks
Beverley Road - Brunswick Arcade04 October 202101 September 2022Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022.HCC - MP&I
Bishop Lane16 May 202219 May 2022Install new water supply connection. Full road closure. Local diversion in place.Yorkshire Water
Carr Lane (About Us event)30 April 202206 May 2022Carr Lane closed from junction with Chariot Street to junction with Queens Dock Avenue, 8pm-11.30pm daily. Diversion in place. About Us event
Charles Street04 April 202229 April 2022Works between Francis Street and Bridlington Avenue, including work in the carriageway and footpath. Removal of existing line markings, installation of new gullies and kerbs to construct off-road cycle track. New surfacing and line markings. Multi-way signals, to be manned at peak times. HCC - MP&I
Great Union Street23 May 202226 June 2022Resurfacing / concrete repairs. Full road closure. Access to be maintained at all times for businesses via A63 / Clarence Street.HCC - MP&I
Hall Road26 April 202226 April 2022Telecoms pole maintenance. Two-way signals in place from 9.30am-3.30pm.O2 (GS Hall)
Hessle Road (12-month Scheme)23 August 202104 September 2022Footway reconstruction.HCC - MP&I
Holderness Road (Victor St to Southcoates) (PHASES 1-8)04 January 202211 September 2022Full footway reconstruction scheme.MP&I - Highways Strategy & Design
Hopewell Road14 March 202229 April 2022Concrete repairs and carriageway resurfacing. Road closure from Slaveley Road junction to Taylor Avenue.HCC - MP&I
Howdale Road - Phase 226 April 202204 May 2022Trench repair on 2nd half of carriageway. Multi-way signals. Junction of Oaktree Drive. 8am start on Sunday. Traffic management to be removed once concrete has cured.Streetscene Highway Operations
Ings Road09 May 202219 May 2022Lane closure in place entrance between 9am and 3pm from the junction of Eglington Avenue to Crooked Billet car park entrance.Northern Gas Network
Stoneferry Rd Scheme - Woodhall Street to Lorraine Street01 April 202101 August 2022Major Improvement Scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed.HCC - MP&I
Stoneferry Rd Scheme - Chamberlain Road to Bandstand Roundabout23 April 202101 August 2022Major improvement scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed.HCC - MP&I / Colas
Stoneferry Rd Scheme - Sutton Road20 April 202222 April 2022Removal of existing splitter islands in the junction of Sutton Road and Leads Road. night. Multi-way signals. Works will take place 7pm to 6am.HCC - MP&I COLAS
Stoneferry Rd Scheme - Leads Road25 April 202229 July 2022Renew footpaths and kerbs. Leads Road closed westbound between Rotterdam Road and Bandstand Roundabout during works.

HCC - MP&I COLAS
Stoneferry Rd Scheme - Leads Road29 July 202201 August 2022Carriageway resurfacing. Leads Road closed in both directions between Rotterdam Road and Bandstand Roundabout from 7pm on Friday 29 July to 6am on Monday August 1.HCC - MP&I COLAS
Stoneferry Rd Scheme - Sutton Road03 May 202201 July 2022Reconstruction of the new junction under temporary traffic lights to enable removal of the existing permanent traffic signals. Multi-way signals to run in phases to help minimise disruption. Leads Road / Sutton Road junction.HCC - MP&I
Wincolmlee15 April 202228 April 2022Emergency works. Low-voltage mains cable fault. Two-way signals between junction of George Street and Scott Street.Northern Power Grid
Wincolmlee18 April 202229 April 2022Works originally postponed due to gas leak. Power main replacement scheme. Multiway signals, junction of Wincomlee/ Air Street / Bank Side.Northern Power Grid