Here is the latest breakdown of scheduled and emergency works taking place across Hull over the next few weeks. All works are subject to change. For the latest updates:
- Visit National Highways for more information on planned roadworks, or follow them on Twitter @HighwaysYORKS
- Follow @hullccnews on Twitter
- Follow the Hull City Council Facebook page
- Check one.network before travelling.
| A63 improvement scheme – St James Street to Market Place | 01-May-20 | 01-May-25 | Major A63 Improvement scheme – full infrastructure change. Lane and road closures until completion of scheme. | National Highways | 
| A63 improvement scheme – Commercial Road | 26-Oct-21 | 30-Apr-24 | Enable H&S and safe systems of works for operatives working on the scheme. Road closure in place. | National Highways | 
| A63 Castle Street – between Daltry Street and Roger Millward Way | 10-Mar-24 | 06-Apr-24 | Various overnight closures to complete work at Market Place and Queen Street junction and other essential works. To find our more, visit https://nationalhighways.co.uk/our-roads/yorkshire-and-north-east/a63-castle-street/ | National Highways | 
| A63 – Queen Street | 11-Mar-24 | 10-May-24 | Castle Street improvement scheme. Full closure of Queen Street on slip (traffic will have no access on to the A63 westbound) Full diversion route will be in place. | National Highways | 
| Barnes Way | 11-Mar-24 | 27-Mar-24 | Utility connections outside the entrance to the new housing development. Two-way signals in place. | Gas Transportation Company | 
| College Street | 14-Mar-24 | 22-Mar-24 | Telecoms maintenance at the junction of Lowgate. Multi-way signals in place. | MS3 | 
| Coventry Road | 04-Mar-24 | 17-May-24 | Installing a new pipe, manhole and connecting onto the existing combined sewer network. Part of the Living with Water Aqua Green Scheme. Road closure in place. | Yorkshire Water | 
| Henry Boot Way | 24-Mar-24 | 24-Mar-24 | Telecoms maintenance at the junction of Priory Way. Contraflow traffic management in place. | Connexin | 
| Hotham Road North | 03-Apr-24 | 03-Apr-24 | Telecoms maintenance. Road closure at the junction of Bricknell Avenue. | Hutchison 3G Limited | 
| Mount Pleasant | 24-Mar-24 | 24-Mar-24 | Excavate to clear blockage between Courtney Street and Mount Pleasant roundabout. Two-way signals in place. | Hutchison 3G Limited | 
| Midmere Avenue | 25-Mar-24 | 26-Mar-24 | Essential carriageway maintenance. Road closure at the junction of Leads Road. | Hull City Council | 
| Manor Road | 05-Feb-24 | 26-Apr-24 | Installing a new pipe, manhole, and connecting onto the existing combined sewer network outside number 82 and 84. Part of the Living with Water Aqua Green Scheme. Road closure in place. | Yorkshire Water | 
| Moorhouse Road | 11-Mar-24 | 14-Jun-24 | Installing a new pipe and manhole on the carriageway and connecting onto the combined sewer. Part of the Living with Water Aqua Green Scheme. Road closure in place. | Yorkshire Water | 
| National Avenue | 11-Mar-24 | 29-Mar-24 | Gas main maintenance at the junction of Wises Farm Road. Multi-way signals in place. | Northern Gas Networks | 
| Spring Bank | 25-Mar-24 | 19-Apr-24 | Cable upgrade scheme at the junction of Norwood Street. Lane closure in place from 9.30am to 3.30pm only. | Northern Powergrid | 