Essential roadworks taking place in Hull are “vital to improve our transport system for better and safer journeys in the future”, says the councillor in charge of the roads.

Critical gas infrastructure repair works have now completed in Lowgate, and other works are coordinated with the relevant organisations undertaking the works across the network to avoid pinch points whenever possible.

Works in Cottingham Road have also been extended due to the poor state of the road, and will now complete on Sunday 27 June. In order to minimise impact to motorists, temporary traffic lights will be installed to control traffic flow and keep queues to a minimum.

Improvement works to cycle lanes in Holderness Road will also be starting from Monday 21 June, with safer measures for cyclists beginning in Southcoates Lane to Summergangs Road.

As part of the mitigation works identified for the council’s road network by Highways England, works will be carried out to install new part-time traffic signals on two stretches of the Hessle Road and Madeley Street roundabout.

This will improve car journeys for motorists using Rawlings Way and Hessle Road as a diversion route for the A63 works.

In order to complete this work Hessle Road will be closed on Sunday 20 June from 10pm-4am to allow the technology to be installed. A signed diversion route will be in place for motorists.

Once completed, these works will offer not only offer significantly improved travel options, but more reliable gas and electricity supplies across the city.

Councillor Dean Kirk, portfolio holder for transportation, roads, highways and flood prevention, said: “Hull’s ambitious project to improve its transport system continues this week as essential major works take place across the city.

“They include works at the A63 and Stoneferry Corridor and also critical utility repairs.

“The works are being undertaken by organisations including Highways England, Northern Gas Networks and Hull City Council, with scheduled works from Northern Powergrid.

“We understand that roadworks can be frustrating for motorists, however these works are essential if we are to improve our transport system for better and safer journeys in the future. We apologies for any inconvenience to drivers in the meantime.”

Motorists are advised to plan their journey before travelling using One.Network, and to keep up-to-date with Stoneferry Corridor works download the Hello Travaux app on the App Store on Google Play.

Below is a breakdown of the roadworks currently taking place in Hull.

Location Start Date Due Date Organisation Current Status
A63 Castle Street – From St James Street to Market Place. May 2020 May 2025 Highways England On track
A63 Castle Street 14 June 2021 3 July 2021 Highways England Requested informally
Stoneferry Road – Foster St to Sutton Road Commenced 28 May 2022 Hull City Council On track
Woodhall Street 10 May 2021 25 June 2021 Hull City Council On track
Holwell Road to Mounty Pleasant junction 23 April 2021 25 June 2022 Hull City Council On track
Cottingham Road 24 May 2021 27 June 2021 Hull City Council Extended by 9 days
Cranbrook Avenue 24 May 2021 11 July 2021 Hull City Council Extended by 35 days
Greenwood Avenue 24 May 2021 16 July 2021 Northern Gas Networks On track
Stockholm Road & West Carr Lane 08 June 2021 25 June 2021 Northern Powergrid On track
Wincolmlee (junction of Cumberland St) 09 June 2021 18 June 2021 Northern Gas Networks On track
Wiltshire Road 14 June 2021 22 August 2021 Hull City Council On track
South Street, Carr Lane & Paragon Street 14 June 2021 2 July 2021 Northern Gas Networks On track
Hessle Road 20 June 2021 21 June 2021 Hull City Council On track
Madeley Street & Rawlings Way 20 June 2021 20 June 2021 Hull City Council Agreed
Humber Street & High Street 21 June 2021 7 Oct 2021 Hull City Council On track
Alfred Gelder Street, Clarence Street and Holderness Road (cycle lanes) 21 June 2021 5 August 2021 Hull City Council On track
Witham 5 July 21 09 July 21 Hull City Council Agreed
Wincolmlee 30 June 2021 06 July 2021 Northern Powergrid Agreed
Hawthorn Ave – Chalk Lane Level Crossing 27 June 21 29 Jun 21 Network Rail Agreed
Dunvegan Road 28 June 2021 15 August 2021 Hull City Council Agreed
Priory Way October 2021 August 2022 Hull City Council Planned
Sutton Road June 2021 December 2021 Hull City Council Planned
Priory Road 8 Aug 2021 20 Sept 2021 Hull City Council Planning stage
Lowgate (outside Guildhall) 19 July 2021 19 July 2021 Hull City Council Planning stage

 