After significant rainfall affected work on the Stoneferry improvement scheme on Wednesday night, resurfacing in West Carr Lane will now require an extra night to be completed.
This will also have knock-on effect on previously announced work on Holwell Road/Sutton Road.
- Work on West Carr Lane is now expected to be completed overnight on Friday 18 March (7pm-6am).
- Work on Holwell Road/Sutton Road will now begin on Monday 21 March (7pm-6am).
Below is a breakdown of roadworks taking place across Hull over the next few weeks. All works are subject to change, so motorists are also advised to check one.network for the latest updates.
26th Avenue / Greenwood Ave | 28-Mar-22 | 31-Mar-22 | Telecoms pole installation. Junction of Greenwood Avenue (footway). Multi-way Signals. Activities to take place between 7pm-11pm on day 1, then 9.30am-3.30pm on day 2. Day 3 and 4, no carriageway incursion. | T-Mobile Ltd - Ericsson |
A63 improvement scheme - St James Street to Market Place | 01 May 2020 | 01 May 2025 | Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. | National Highways |
A63 improvement scheme - Brighton Street to Roger Millward Way | 07 March 2022 | 25 March 2022 | Road closure eastbound from Brighton Street to Roger Millward Way and westbound from Roger Millward Way to Daltry Street. Weeknights from 8pm - 6am. | 40 Seven Ltd |
A63 improvement scheme - Commercial Road | 26 October 2021 | 30 April 2022 | Enable H&S and safe systems of works for operatives working on the scheme. | National Highways |
Bellfield Avenue | 10 January 2022 | 06 April 2022 | Multi-way signals at the junction with Savoy Road. Manned between traffic sensitive times. | HCC - MP&I |
Bellfield Avenue | 06 March 2022 | 08 April 2022 | Road closure for carriageway resurfacing. Works to take place between 7pm - 6am. Local diversion in place. | Section 278 |
Beverley Road | 07 March 2022 | 22 April 2022 | Gas Main replacement scheme. Inbound from city Boundary to Mizzen Road. Lane Closure | Northern Gas Networks |
Beverley Road - Brunswick Arcade | 04 October 2021 | 01 September 2022 | Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022. | HCC - MP&I |
Hall Road | 15 March 2022 | 25 March 2022 | Cherry picker to access telecoms mast for testing and maintenance works from 9.30am-3.30pm approx 100m west of Thorpepark Road. Two-way signals. | O2 (GS Hall) |
Hessle Road (12-month Scheme) | 23 August 2021 | 04 September 2022 | Footway reconstruction. | HCC - MP&I |
High Street | 18-Mar-22 | 19-Mar-22 | The Awakenings event. Road closure between Liberty Lane and Gandhi Way, 6pm-midnight | Freedom Festival |
Holderness Road (Victor St to Southcoates) (PHASES 1-8) | 04 January 2022 | 11 September 2022 | Full footway reconstruction scheme. | MP&I - Highways Strategy & Design |
Holwell Road | 24-Mar-22 | 25-Mar-22 | Approx 25m south of Goodhart road. Minor, non-excavation works. Two-way traffic lights in place 9.30am-3.30pm. | O2 (GS Hall) |
Hopewell Road | 14 March 2022 | 24 April 2022 | Concrete repairs and carriageway resurfacing. Road closure from Slaveley Road junction to Taylor Avenue. | HCC - MP&I |
Humber Street | 07 February 2022 | 19 March 2022 | Installation of bollards. Works span width of footway and carriageway outside Dinostar. Work will be done in sections to maintain pedestrian walkway. | HCC - MP&I |
Lowgate Footway Scheme - West / East Footway | 22 October 2021 | 16 April 2022 | Footway repair scheme. Scheme delayed due to signal failure on A63. Northbound closure. Current traffic management set-up to remain in place for duration of scheme. | HCC - MP&I |
Queens Dock Avenue | 18-Mar-22 | 19-Mar-22 | The Awakenings event. Road Closure between Carr Lane and George Street. 6pm - 11pm. | Freedom Festival |
Rawlings Way | 04-Apr-22 | 04-Apr-22 | Cutting of new loops. Multi-way signals. Working hours 7pm - 11pm | StreetScene - Traffic Signals |
Stoneferry Rd Scheme - Woodhall Street to Lorraine Street | 01 April 2021 | 01 April 2022 | Major Improvement Scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed. | HCC - MP&I |
Stoneferry Rd Scheme - Chamberlain Road to Bandstand Roundabout | 23 April 2021 | 01 April 2022 | Major improvement scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed. | HCC - MP&I / Colas |
Stoneferry Rd Scheme - West Carr Lane | 15 March 2022 | 19 March 2022 | Surfacing to West Carr Lane. Road closure from NR Burnett entrance to junction with Stoneferry Road / Holwell Road Closures from 7pm to 6am, Mon to Fri nights. | HCC - MP&I / Colas |
Stoneferry Rd Scheme - Sutton Road | 21 March 2022 | 24 March 2022 | Surfacing of Sutton Road, Road closure eastbound from junction with Holwell Roundabout for approx 120m. | HCC - MP&I / Colas |
Stoneferry Rd Scheme - Holwell Road | 21 March 2022 | 24 March 2022 | Surfacing of Holwell Road. Road closure northbound from junction with Sutton Road. | HCC - MP&I / Colas |
Wincolmlee (Phase 2) | 16 March 2022 | 28 March 2022 | Road closure for new connection and cable upgrades. Works delayed due to gas leak, completion date could change. | Northern Powergrid |