People are being reminded to plan their journeys before travelling around Hull this weekend.
As the city undergoes vital improvements to the road and transport infrastructure, motorists are advised to plan their journey before travelling using One.Network, and to keep up-to-date with Stoneferry Corridor works download the Hello Travaux app on the App Store on Google Play.
And as Hull City Council moves towards developing a more inclusive transport strategy which encourages a greener form of travel, the local authority want to hear your views.
The council wants to know about issues on local roads, how you travel, why you choose your preferred mode of transport, and what, if anything, would make you change the way that you travel.
The survey can be access via the Hull City Council website.
Councillor Dean Kirk, portfolio holder for transportation, roads, highways and flood prevention, said: “We want people who live, visit and travel around the city to share their views on how we develop plans to implement a more sustainable and accessible transport system for everyone, and the feedback you provide in this survey is absolutely critical to this.”
Important changes to NHS covid permits will also come into effect next week. In line with Government guidance these passes will no longer be valid from Monday 19 July. Letters will be issued to those motorists affected by this change.
Below is a breakdown of the roadworks currently taking place in Hull.
Location | Start date | Completion date | Details of work | Organisation | Current status |
A63 Castle Street – From St James Street to Market Place.
|
May 2020 | May 2025 | Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGV’s in city centre | Highways England | On track |
Daltry Street and Roger Millward Way | 22, 23 & 26 July | Overnight lane closures (8pm – 6am) | Highways England | On track | |
Stoneferry Road – Foster St to Sutton Road | Commenced | 28 May 2022 | Installation of the Stoneferry Road Corridor capital programme scheme | Hull City Council | On track |
Woodhall Street | 10 May 2021 | 16 July 2021 | Installation of the Stoneferry Road Corridor capital programme scheme | Hull City Council | Extended by 22 days |
Holwell Road to Mount Pleasant junction (Stoneferry Corridor works) | 23 April 2021 | 25 June 2022 | Installation of the Stoneferry Road Corridor | Hull City Council | On track |
Greenwood Avenue | 24 May 2021 | 20 July 2021 | Replacement of gas pipes in footpaths | Northern Gas Networks | On track |
Wiltshire Road | 14 June 2021 | 22 August 2021 | Excavate existing concrete carriageway and carry out any required concrete repairs | Hull City Council | On track |
South Street, Carr Lane & Paragon Street | 14 June 2021 | 30 July 2021 | Essential gas works | Northern Gas Networks | Additional works agreed |
Humber Street & High Street | 21 June 2021 | 7 Oct 2021 | Reconstruction of footpaths and road surface | Hull City Council | On track |
Dunvegan Road | 28 June 2021 | 15 August 2021 | Essential footway repairs | Hull City Council | On track |
Sutton Road/Leads Road (Stoneferry Corridor works) | June 2021 | December 2021 | Reconstruction of junction | Hull City Council | On track |
Alfred Gelder Street/Clarence Street | 13 July 2021 | 27 July 2021y | Cycle lanes, anti-skid & line removal | Hull City Council | On track |
Holderness Road (Ings to Diadem) | 19 July 2021 | 30 July 2021 | Installation of cycle lane | Hull City Council | Planned |
Spring Bank West | 19 July | 11 October 2021 | Essential gas works in footway – will be removed for Hull Fair | Northern Gas Networks | Planned |
Wincolmlee | 26 July | 30 July | Essential works – new connection | Northern Powergrid | Planned |
High Street | 2 August 2021 | 6 August 2021 | Road closure will be in place | Yorkshire Water | Planned |
Priory Road | 8 August 2021 | 20 Sept 2021 | Carriageway & footway re-construction & bus lanes/ parking bays | Hull City Council | Planned |
Brunswick Arcade (Beverley Road) | 9 August | November 2022 | Lane closures from October 2021 onwards | Hull City Council | Planned |
Lowgate (outside Guildhall) | September 2021 | September 2021 | Crane required to access the clock tower – diversion routes in place | Hull City Council | Planned |
Bowl Alley Lane | 20 September 2021 | 29 October 2021 | Footway improvements – road closure | Hull City Council | Planned |
Priory Way | October 2021 | August 2022 | Major widening and construction of three signalised junctions | Hull City Council | Planned |
Air Street | Oct 2021 | Oct 2021 | Essential gas works | Northern Gas Networks | Planned |
Silver Street | 1 November 2021 | 30 November 2021 | Installing automatic bollards | Hull City Council | Planned |