A63 improvement scheme - St James Street to Market Place | 01 May 2020 | 01 May 2025 | Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. | National Highways |
A63 improvement scheme - Commercial Road | 26 October 2021 | 30 April 2024 | Enable H&S and safe systems of works for operatives working on the scheme. | National Highways |
Beverley Road - Brunswick Arcade | 04 October 2021 | 01 April 2023 | Brunswick Arcade demolition. Lane closures | HCC - MP&I |
Beverley Road | 11 July 2022 | 29 July 2022 | Junction improvement scheme. | HCC & MP&I |
Carr Lane | 04 July 2022 | 17 July 2022 | Replacement of rocking / damaged kerbs and channels. One-way closure to eastbound traffic. Existing traffic signals to be unaffected. | MP&I ST-GROUP |
Chamberlain Road | 18 July 2022 | 21 July 2022 | Replacment of toucan crossing traffic signals at Foredyke Stream cycle track. Two-way temporary signals. | StreetScene - Traffic Signals |
Chamberlain Road | 02 August 2022 | 04 August 2022 | Replacment of toucan crossing traffic signals at Hornsea cycle track. Two-way temporary signals. | StreetScene - Traffic Signals |
Field Street | 27 June 2022 | 18 July 2022 | Gas mains replacement. Road closure to end on completion of works across the junction. | East Riding DSP Replacement |
Hawthorne Avenue | 16 August 2022 | 19 August 2022 | Level crossing and track survey. Lane closure with two-way signals from 11pm - 5.30am. | Network Rail |
Hessle Road (12-month Scheme) | 23 August 2021 | 04 September 2022 | Footway reconstruction. | HCC - MP&I |
High Street | 16 May 2022 | 30 July 2022 | Laying ducting, kerbs/ edgings, installation of cobbled paving under Myton Bridge. Multi-way signals. | National Highways |
High Street | 30 July 2022 | 30 July 2022 | Hull Festival of Archaeology. Closure of High Street. Local diversion in place in conjuction with Pride Event. | HCC |
Holderness Road (Victor St to Southcoates) (PHASES 1-8) | 04 January 2022 | 11 September 2022 | Full footway reconstruction scheme. | MP&I - Highways Strategy & Design |
Holderness Road | 13 June 2020 | 29 July 2022 | Gas mains replacement work. From junction of Franklin Street to opposite junction of Williamson Street. Lane closure in carriageway. Footway closed (a walkway will be available). Access/egress to all junctions. TM to be removed as works progress along Holderness Road. All works areas to be a maximum of 100m. | East Riding DSP Replacement/ Northern Gas Networks |
James Reckitt Avenue | 11 July 2022 | 22 July 2022 | Excavate & install 8 telecoms poles. o/s Malet Lambert School, o/s number 591, o/s number 601, opposite number 534, o/s number 552, o/s number 570, o/s number 590 & o/s telecoms pole. Works will take place 9.30am-3.30pm weekdays. Stop & Go to be in place. | Connexin Limited |
Maybury Road | 20 July 2022 | 20 July 2022 | Carriageway repair works. Stop & Go at junction with Holderness Road. Work to take place between 9.30am and 3.30pm | StreetScene - Highway Operations |
Naylor's Row | 25 July 2022 | 19 August 2022 | Gas mains replacement. Cycle lane closure - traffic flow not affected. | Northern Gas Netowrk |
Perth Street West | 25 July 2022 | 05 August 2022 | Renew cable. Two-way signals to be manned during working hours (8am - 6pm). | NPG |
Priory Way | 01 April 2022 | 31 March 2023 | Major improvement scheme. | HCC - MP&I |
Robson Way | 22 September 2022 | 28 September 2022 | Install 5G cabinet. Road closure approximately 40m from junction with Wawne Road. Local diversion in place. | T-mobile |
Saltshouse Road | 25 July 2022 | 26 August 2022 | Replace gas main. Temporary two-way signals outside Coniston Lodge lights to be manually controlled during works (7.30am to 6pm Mon to Fri; 8am to 3pm Sat/Sun). | East Riding DSP Replacement |
Stoneferry Rd Scheme - Woodhall Street to Lorraine Street | 01 April 2021 | 01 September 2022 | Major Improvement Scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall Street junction are now completed. | HCC - MP&I |
Stoneferry Rd Scheme - Chamberlain Road to Bandstand Roundabout | 23 April 2021 | 01 September 2022 | Major improvement scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall Street junction are now completed. | HCC - MP&I / Colas |
Stoneferry Rd Scheme - Leads Road | 25 April 2022 | 29 July 2022 | Renew footpaths and kerbs. Leads Road closed westbound between Rotterdam Road and Bandstand Roundabout during works. | HCC - MP&I COLAS |
Stoneferry Rd Scheme - Sutton Road | 03 May 2022 | 12 August 2022 | Reconstruction of the new junction under temporary traffic lights to enable removal of the existing permanent traffic signals. Multi-way signals to run in phases to help minimise disruption. Leads Road / Sutton Road junction. | HCC - MP&I |
Stoneferry Rd Scheme - Holwell Road/Stoneferry Road | 27 July 2022 | 28 July 2022 | Carriageway resurfacing. Stoneferry Road (southbound) closed overnight (7pm - 6am) from Bandstand Roundabout to Ferry Lane Roundabout. Lane closure on Holwell Road approach to Bandstand Roundabout. | StreetScene - Traffic Signals |
Stoneferry Rd Scheme - Leads Road / Sutton Road junction | 28 July 2022 | 03 August 2022 | Carriageway resurfacing. Overnight closure of northern section of junction. Works to take place Mon-Fri between 7pm - 6am. Sutton Road to remain open under two-way signals. | MP&I Colas |
Stoneferry Rd Scheme - Leads Road / Sutton Road junction | 03 August 2022 | 09 August 2022 | Carriageway resurfacing. Overnight road closures on southern section of junction. Works to take place Mon-Fri between 7pm - 6am. Sutton Road to remain open under two-way signals. | MP&I Colas |
Stoneferry Rd Scheme - Leads Road / Sutton Road junction | 09 August 2022 | 10 August 2022 | Carriageway resurfacing. Overnight closure (7pm-6am) of whole junction. Sutton Road to remain open under two-way signals. | MP&I Colas |
Stoneferry Rd Scheme - Leads Road / Sutton Road junction | 10 August 2022 | 11 August 2022 | Carriageway resurfacing. Overnight closure (7pm - 6am) of northern section of junction. Sutton Road to remain open under two-way signals. | MP&I Colas |
Stoneferry Rd Scheme - Leads Road / Sutton Road junction | 11 August 2022 | 13 August 2022 | Carriageway resurfacing. Overnight closure of southern section of junction. Works to take place weeknights between 7pm - 6am. Sutton Road to remain open under two-way signals. | MP&I Colas |
Stoneferry Rd Scheme - Leads Road | 13 August 2022 | 14 August 2022 | Carriageway resurfacing. Full weekend closure of Leads Road between Bandstand Roundabout & Rotterdam Road. Closure will start at 7am Saturday and will be removed by midnight on Sunday. | MP&I Colas |
Sutton Road | 22 August 2022 | 25 August 2022 | Replacement of toucan crossing traffic signals. Temporary two-way signals between Leads Road junction and Holwell Roundabout. | StreetScene - Traffic Signals |
Thomas Street | 11 July 2022 | 25 July 2022 | Gas mains replacement. Road closed. Closure to end on completion of works across the junction. | Northern Gas Netowrk |
Wincolmlee / Cumberland Street | 20 June 2022 | 17 July 2022 | Carriageway resurfacing and concrete repairs. Road closures on Cumberland Street (between Swann Street and Wincolmlee) and Wincolmlee (between Cumberland Street and Lincoln Street). | HCC- MP&I |
Wilberforce Drive | 30 July 2022 | 30 July 2022 | Pride Event. Full closure of Wilberforce Drive, Guildhall Road & Queens Dock Avenue. Short-duration closures of Alfred Gelder Street, Lowgate, Bond Street and George Street during parade. Local diversion in place. | Hull Pride |
Worship Street | 11 July 2022 | 05 July 2023 | Conversion of former Central Fire Station. No access to/from Freetown Way. Local diversion in place. | esteem |