Hull City Council weekly traffic and travel update – 13 September

Here is the latest breakdown of scheduled and emergency works taking place across Hull over the next few weeks. All works are subject to change. For the latest updates:

LocationStart dateDue dateSummary of worksUtility/HCC
A63 improvement scheme – St James Street to Market Place01-May-2001-May-25Major A63 Improvement scheme – full infrastructure change. Lane and road closures until completion of scheme.National Highways
A63 – Market Place13-Sep-2413-Oct-24Castle Street improvement scheme. Full closure of the Market Place entry slip road. Full diversion route will be in place.National Highways
Anlaby Park Road South23-Sep-2415-Nov-24Carriageway resurfacing from Tilbury Road to number 174. Road closure in place.Hull City Council (Major Projects)
Barnes Way23-Sep-2404-Oct-24Completing gas, water, and electric services to plots 84-97. Multi-way signals in place at the junction of Connaught Road to site entrance.Independent Water Networks Limited/Gas Transportation Company/Electricity Network Company
Bishop Lane 09-Sep-2420-Sep-24New mains cable installation. Road closure in place.Northern Powergrid
Chanterlands Avenue19-Sep-2401-Oct-24Dig road crossing outside 39/41 to the side of 142 Newstead Street. Multi-way signals in place between 9.30am and 3.30pm.Grain
Chapel Lane20-Aug-2418-Sep-24New mains cable installation at the junction of Lowgate. Road closure in place.Northern Powergrid
Clifford Avenue09-Sep-2418-Sep-24Road closure to rectify defect at the junction of James Reckitt.Yorkshire Water
Fountain Road02-Sep-2420-Sep-24Gas main replacement at the junction of Main Street. Multi-way signals in place.Northern Gas Networks
Holderness Road20-Aug-2418-Sep-24Gas main replacement at the junction of Summergangs Road to opposite 532 Holderness Road. Lane closure in place.Northern Gas Networks
Hotham Road South23-Sep-2420-Dec-24Manhole construction. Road closure in place.Yorkshire Water
Lowgate/Alfred Gelder Street20-Aug-2418-Sep-24To install a new mains cable at the junction of Alfred Gelder Street. Multi-way signals in place.Northern Powergrid
Lowgate18-Sep-2402-Oct-24New mains cable installation from the church to the junction of Scale Lane. Two-way signals in place.Northern Powergrid
Main Street02-Sep-2420-Sep-24Connection only due to works on Fountain Road. Multi-way signals in place.Northern Gas Networks
Marfleet Lane12-Sep-2418-Sep-24To repair burst water main at the junction of Regis Court/Marfleet Lane. Multi-way signals in place.Yorkshire Water
Moorhouse Road16-Sep-2420-Sep-24Interim to permanent reinstatement outside number 238 and 240 Moorhouse Road. Road closure in place.Yorkshire Water
Mount Pleasant10-Sep-2420-Sep-24New connection adjacent to the junction of Dansom Lane North. Two-way signals in place.Northern Powergrid
Mount Pleasant23-Sep-2426-Sep-24Utility asset works opposite The Car Lot. Two-way signals in place.Hutchison 3G Limited
National Avenue09-Sep-2418-Sep-24Rectify reinstatement outside 221 National Avenue. Two-way signals in place.Yorkshire Water
New Bridge Road 14-Sep-2415-Sep-24Rail works. Multi-way signals in place.Network Rail
Orchard Park Road16-Sep-2427-Sep-24Resurfacing scheme from Ellerburn Avenue to eastern junction of Hall Road. Road closure in place.Hull City Council (Major Projects)
Wincolmlee09-Sep-2404-Oct-24Asset replacement at the junction of Oxford Street to Cumberland Street. Road closure in place.Northern Gas Networks