Paving works will take place in Hull's Old Town.

Upcoming roadworks taking place in Hull

Essential works to improve Hull’s infrastructure continue this week, with major works taking place as part of the Highways England A63 scheme.

From Monday 16 August motorists will be diverted between 8pm and 6am from Daltry Street to Roger Millward Way.

The work taking place will involve removing the Porter Street pedestrian crossing and the installation of a temporary one. They will also continue changing the layout at the Mytongate junction so more work can be carried out during the day.

“Councillor Dean Kirk, portfolio holder for transportation, roads, highways and flood prevention, said: “These are significant works and motorists are advised to allow extra time for their journeys.”

And there is still time to have your say in the transport survey which closes on Monday 23 August.

“Councillor Kirk said: “We want people who live, visit and travel around the city to share their views on how we develop plans to implement a more sustainable and accessible transport system for everyone, and the feedback you provide in this survey is absolutely critical to this.”

Motorists are advised to plan their journey before travelling using One.Network, and to keep up-to-date with Stoneferry Corridor works download the Hello Travaux app on the App Store on Google Play.

A breakdown of planned works taking place across the city has been detailed below:

Location Start date Completion date Details of work Organisation Current status
A63 Castle Street – From St James Street to Market Place.

 

May 2020 May 2025 Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGV’s in city centre Highways England On track
Stoneferry Corridor – Woodhall Street – Lorraine Avenue Started 28 May 2022 Installation of the Stoneferry Road Corridor works Hull City Council On track
Stoneferry Corridor – Chamberlain Road to Bandstand Roundabout 23 April 2021 25 June 2022 Installation of the Stoneferry Road Corridor works Hull City Council On track
Stoneferry Corridor – Sutton Road – Leads Road June 2021 17 September 2021 Installation of the Stoneferry Road Corridor works Hull City Council On track
Wiltshire Road 14 June 2021 17 October 2021 Excavate existing concrete carriageway and carry out any required repairs

 

Hull City Council Extended
Humber Street & High Street 21 June 2021 7 Oct 2021 Reconstruction of footpaths and road surface Hull City Council On track
Dunvegan Road 28 June 2021 15 August 2021 Essential footway repairs Hull City Council On track
Holderness Road (Ings to Diadem) 19 July 20 August 2021 Installation of cycle lane Hull City Council On track
Spring Bank West 19 July 2021 24 September 2021 Essential gas works in footways Northern Gas Networks On track
Priory Road 2 August 2021 27 September 2021 Carriageway & footway re-construction & bus lanes/ parking bays Hull City Council On track
Commercial Road 2 August 2021 25 October 2021 A63 improvement scheme, no left turn from commercial road onto A63. Access via Daltry Street. Highways England On track
Saltshouse Road 12 August 2021 25 August 2021 Cable diversion. Northern Powergrid Planned
Ferry Lane 16 August 2021 20 August 2021 Installation of barriers in central reservations – lane closure either side of road Hull City Council Planned
Daltry Street and Roger Millward Way 16 August 2021 Monday 6 September 2021 A63 will be closed between Daltry Street and Roger Millward Way between 8pm and 6am. The work will involve removing the Porter Street pedestrian crossing and installing the temporary one. Highways England Planned
Brunswick Arcade (Beverley Road) 16 August 2021 November 2022 Lane closures from October 2021 onwards Hull City Council Planned
Greenwood Avenue 16 August 2021 18 August 2021 Mobile mast works – traffic management T-Mobile Planned
South Street – Carr Lane, Osborne Street – Anne Street 23 August 2021 25 August 2021 Resurfacing scheme with overnight works Hull City Council Planned
Beverley Road -Greenwood Avenue to Hall Road outbound 23 August 2021 20 September 2021 Construction of cycle track. Lane closures in place 9.30am – 3.30pm Hull City Council Planned
Hessle Road 23 August 2021 September 2022 Reconstruction of pavements Hull City Council Planned
Sutton Road flyover 25 August 2021 26 August 2021 Essential bridge maintenance. Evening road closure (7pm-6am) Hull City Council Planned
Holderness Road 6 September 2021 September 2022 Reconstruction of pavements Hull City Council Planned
Lowgate (outside Guildhall) September 2021 September 2021 Crane required to access the clock tower – diversion routes in place Hull City Council Planned
Queen Street 20 September 2021 27 September 2021 Resurfacing scheme Hull City Council Planned
Beverley Road -Greenwood Avenue to city Boundary outbound 21 September 2021 13 October 2021 Construction of cycle track. Lane closures in place 9.30am – 3.30pm Hull City Council Planned
Inglemire Lane & Hall Road 27 September 2021 10 October 2021 Road resurfacing – temp traffic lights Hull City Council Planned
Air Street 27 September 2021 22 October 2021 Essential gas works – road closure required Northern Gas Networks Planned
Beverley Road – Hall Road to city Boundary outbound 14 October 2021 4 November 2021 Construction of off line cycle track. Hull City Council Planned
Beverley Road – Mizzen Road to Hall Road inbound 22 October 2021 17 November 2021 Construction of cycle track. Lane closures in place 9.30am – 3.30pm Hull City Council Planned
Priory Way October 2021 August 2022 Major widening and construction of three signalised junctions Hull City Council Planned
Bowl Alley Lane October 2021 October 2021 Pavement improvements – road closure Hull City Council Planned
Silver Street 4 January 2022 31 January 2022 Installing automatic bollards Hull City Council Planned

 