The Stoneferry Corridor improvement project continues next week, with some changes to previously scheduled works.
Surfacing works to Chamberlain Roundabout, which were due to finish on Friday December 10, will now be completed by 6am on Wednesday 15 December. Arrangements for access to Lorraine Street during the closures will remain unaltered. Read our previous story here
From 7pm on Wednesday December 15, overnight resurfacing work will begin in Stoneferry Road and Ferry Lane.
Motorists should expect road closures in the following locations:
- Stoneferry Road northbound between Ann Watson Street and Bandstand Roundabout;
- Ferry Lane westbound from Stoneferry Road to the Stoneferry Bridges.
The work will take place on Wednesday 15 December and Thursday 16 December, from 7pm to 6am each night. Full details here
Resurfacing work to Stoneferry Road southbound and Ferry Lane Roundabout, which was due to start on Monday 13 December, has been delayed until next year.
Below is a breakdown of roadworks taking place across Hull over the next few weeks:
Location | Start Date | Due Date | Reason | Utility/HCC Name |
A63 improvement scheme – Commercial Road | 26/10/21 | 30/4/22 | Enable H&S and safe systems of works for operatives working on the scheme | National Highways |
A63 improvement scheme – St James Street to Market place | 1/5/20 | 1/5/25 | Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre. | National Highways |
Argyle Street | 12/12/21 | 12/12/21 | Disconnect water supply. Footpath closure with walkway in carriageway at exit from NHS car park | Yorkshire Water |
Barham Road | 29/11/21 | 23/1/22 | Carriageway Resurfacing and concrete repairs | HCC – MP&I |
Beverley Road cycle scheme | 14/10/21 | 23/12/21 | Construction of off-line cycle track. Hall Road to City Boundary outbound. Lane closure throughout duration of works. | HCC – MP&I |
Beverley Road – Brunswick Arcade | 4/10/21 | 1/9/22 | Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022 | HCC – MP&I |
Beverley Road | 8/12/21 | 9/12/21 | Slot cutting. Beverley Road outbound between Mizzen Road and Hall Road. Lane closure 9.30am to 3.30pm | StreetScene – Traffic Signals |
Beverley Road | 9/12/21 | 10/12/21 | Slot cutting. Beverley Road inbound to Mizzen Road. Lane closure 9.30am to 3.30pm | StreetScene – Traffic Signals |
Beverley Road – junction with Hall Road | 15/12/21 | 16/12/21 | Application of anti-skid and lining. Multi-way lights 7pm-11pm. | MP&I ARBPMLTD |
Bowlalley Lane | 18/10/21 | 17/12/21 | Footway Scheme. Extended to include carriageway. Road closure | HCC – MP&I |
Hessle Road (12-month Scheme) | 23/8/21 | 4/9/22 | Footway reconstruction | HCC – MP&I |
Holderness Road (Victor St to Southcoates) (PHASES 1-8) | 27/9/21 | 1/11/22 | Full footway reconstruction scheme. | HCC – MP&I |
Holderness Road | 21/12/21 | 23/12/21 | Lane closure for work to existing telecoms site in the central verge near Summergangs Lane. | T-Mobile Ltd |
Holwell Road | 13/12/21 | 17/12/21 | Repairs to concrete surface and roundabout. Lane closures from 9.30am on 13 Dec for duration of work. | HCC – Colas |
Lowgate Footway Scheme – Lowgate | 1/11/21 | 10/1/22 | Footway repair scheme. Closed northbound from A63 to North Church Side. A63 slip road closed. Lane open southbound from Alfred Gelder Street to A63. | HCC – MP&I |
Lowgate Footway Scheme – Market Place | 22/10/21 | 22/12/21 | Footway repair scheme. East footway – no carriageway incursion. Except on occasions, parking bays removed to provide walkway | HCC – MP&I |
Saltshouse Road | 1/11/21 | 12/1/22 | Installation of two new pedestrian refuge islands between Dunvegan Road and Clear View Close | HCC-MP&I |
Southcoates Lane | 8/12/21 | 17/12/21 | Carriageway repair works (near Cundall Close) 9.30am to 3.30pm. Multi-way signals. | Streetscene Highway Operations |
Spring Bank West | 25/10/21 | 18/12/21 | Upgrading network. Opposite Albert Ave to Tile Giant (footway, carriageway) | HCC – Streetscene Signals |
Stoneferry Rd Scheme – Woodhall Street to Lorraine Avenue | 1/4/21 | 28/5/22 | Major Improvement Scheme commissioned by HCC – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed | HCC – MP&I |
Stoneferry Rd Scheme – Chamberlain Road to Bandstand roundabout | 23/4/21 | 25/6/22 | Major improvement scheme commissioned by HCC – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completed | HCC – MP&I COLAS |
Stoneferry Rd Scheme – Bandstand roundabout | 26/11/21 | 29/11/21 | Roundabout closed for road surfacing and repair work from 7pm Friday to 6am Monday. Foredyke Avenue to be two-way with restricted parking. | HCC – MP&I COLAS |
Stoneferry Rd Scheme – Chamberlain Road | 6/12/21 | 15/12/21 | Resurfacing to Chamberlain Road and roundabout. Closure of Chamberlain Road roundabout on Stoneferry Road and along Chamberlain Road to opposite No 194. Access to/from Lorraine Street will be maintained by marshalling. Works to take place overnight. | HCC – MP&I COLAS |
Stoneferry Rd Scheme- Stoneferry Rd/Ferry Lane | 15/12/21 | 18/12/21 | Resurfacing to mainline carriageway. Closures 7pm-6pm: Stoneferry Road northbound between Ann Watson Street and Bandstand Roundabout; Ferry Lane westbound from Stoneferry Road to the Stoneferry Bridges. Two nights with third as contingency. | HCC – MP&I COLAS |
Sutton Road – junction with Leads Road | 14/12/21 | 16/12/21 | Installation of duct crossing across Sutton Road east of junction. Works will take place 9.30am to 3.30pm. Multi-way signals will be manned at all times. | HCC – Colas |
Wincolmlee (Phase 1) | 13/12/21 | 17/1/22 | Essential work to upgrade power supply. Multi-way signals, to be manned during traffic-sensitive times. All traffic management to be removed during Christmas closedown. | Northern Powergrid |