Essential works to improve Hull’s infrastructure continues this week.
A breakdown of planned works taking place across the city has been detailed below, including future works, so motorists can plan their journeys in advance.
The current works are being undertaken by a number of organisations in addition to Hull City Council, including Highways England and Northern Gas Networks, with scheduled works from Yorkshire Water.
The works are coordinated across the network to avoid pinch points, however the works currently taking place are essential.
Councillor Dean Kirk, portfolio holder for transportation, roads, highways and flood prevention, said: “As we approach the summer holidays we understand traffic will be lighter on the roads, and hope that there will be significantly less pressure on our transport network.
“We understand that roadworks can be frustrating for motorists, however these works are essential if we are to improve the city’s infrastructure for better and safer journeys in the future. We apologise for any inconvenience to drivers in the meantime.”
Motorists are advised to plan their journey before travelling using One.Network, and to keep up-to-date with Stoneferry Corridor works download the Hello Travaux app on the App Store on Google Play.
Residents are also reminded to take part in a transport survey, designed to understand the concerns, barriers and opportunities to improve transport in the city.
To have your say, visit the Hull City Council website.
Below is a breakdown of the roadworks currently taking place in Hull.
Location | Start date | Completion date | Details of work | Organisation | Current status |
A63 Castle Street – From St James Street to Market Place.
|
May 2020 | May 2025 | Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGV’s in city centre | Highways England | On track |
Daltry Street and Roger Millward Way | 7 July | Friday 9 July | Overnight lane closures (8pm – 6am) | Highways England | On track |
Stoneferry Road – Foster St to Sutton Road | Commenced | 28 May 2022 | Installation of the Stoneferry Road Corridor capital programme scheme | Hull City Council | On track |
Woodhall Street | 10 May 2021 | 16 July 2021 | Installation of the Stoneferry Road Corridor capital programme scheme | Hull City Council | Extended by 22 days |
Holwell Road to Mount Pleasant junction (Stoneferry Corridor works) | 23 April 2021 | 25 June 2022 | Installation of the Stoneferry Road Corridor | Hull City Council | On track |
Cranbrook Avenue | 24 May 2021 | 11 July 2021 | Roadworks reconstruction & resurfacing
|
Hull City Council | Extended by 35 days |
Greenwood Avenue | 24 May 2021 | 16 July 2021 | Replacement of gas pipes in footpaths | Northern Gas Networks | On track |
Wiltshire Road | 14 June 2021 | 22 August 2021 | Excavate existing concrete carriageway and carry out any required concrete repairs
|
Hull City Council | On track |
South Street, Carr Lane & Paragon Street | 14 June 2021 | 30 July 2021 | Essential gas works | Northern Gas Networks | Additional works agreed |
Humber Street & High Street | 21 June 2021 | 7 Oct 2021 | Reconstruction of footpaths and road surface | Hull City Council | On track |
Wincolmlee | 30 June 2021 | 9 July 2021 | Essential works – new connection | Northern Powergrid | On track |
Dunvegan Road | 28 June 2021 | 15 August 2021 | Essential footway repairs | Hull City Council | On track |
Sutton Road/Leads Road (Stoneferry Corridor works) | June 2021 | December 2021 | Reconstruction of junction | Hull City Council | Delayed |
Clarence Street/Alfred Gelder Street | 13 July 2021 | 27 July 2021y | Cycle lanes, anti-skid & line removal | Hull City Council | On track |
Lowgate (outside Guildhall) | 19 July 2021 | 19 July 2021 | Crane required to access the clock tower – diversion routes in place | Hull City Council | Planned |
Holderness Road (Ings to Diadem) | 19 July 2021 | 30 July 2021 | Installation of cycle lane | Hull City Council | Planned |
Spring Bank West | 19 July | 11 October 2021 | Essential gas works in footway – will be removed for Hull Fair | Northern Gas Networks | Planned |
High Street | 2 August 2021 | 6 August 2021 | Road closure will be in place | Yorkshire Water | Planned |
Priory Road | 8 August 2021 | 20 Sept 2021 | Carriageway & footway re-construction & bus lanes/ parking bays | Hull City Council | Planned |
Brunswick Arcade (Beverley Road) | 9 August | November 2022 | Lane closures from October 2021 onwards | Hull City Council | Planned |
Bowl Alley Lane | 20 September 2021 | 29 October 2021 | Footway improvements – road closure | Hull City Council | Planned |
Priory Way | October 2021 | August 2022 | Major widening and construction of three signalised junctions | Hull City Council | Planned |
Air Street | Oct 2021 | Oct 2021 | Essential gas works | Northern Gas Networks | Planned |
Silver Street | 1 November 2021 | 30 November 2021 | Installing automatic bollards | Hull City Council | Planned |