Weekly roadworks update – May 6

It was announced this week that essential road repairs will begin on Calvert Lane later this month.

The work is due to start on Monday 16 May and is expected to last for eight weeks.

Read the full story

Below is a breakdown of roadworks taking place across Hull over the next few weeks. All works are subject to change. For the latest updates:

LocationStart dateDue dateSummary of worksUtility/HCC name
A63 improvement scheme - St James Street to Market Place01 May 202001 May 2025Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre.National Highways
A63 improvement scheme - Commercial Road26 October 202130 April 2024Enable H&S and safe systems of works for operatives working on the scheme.National Highways
Beverley Road07 March 202206 May 2022Gas Main replacement scheme. Inbound from city Boundary to Mizzen Road. Lane closure.Northern Gas Networks
Beverley Road - Brunswick Arcade04 October 202101 September 2022Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022.HCC - MP&I
Beverley Road/Fountain Road junction09 May 202216 May 2022Work to install delineator blocks. Two nights with temporary three-way signals, followed by four days with cycle track and part footpath closure, followed by two nights under three-way signals. Multi-way lights to be used only between 7pm and 11pm.MP&I ARB (PM) LTD
Bishop Lane16 May 202219 May 2022Install new water supply connection. Full road closure. Local diversion in place.Yorkshire Water
Calvert Lane16 May 202210 July 2022Carriageway resurfacing scheme from approximately 50m north of Boundary Way to Calvert Lane fire station. Road closed. Diversion in place. Access to be maintained at all times.HCC - MP&I
Carr Lane (About Us event)30 April 202206 May 2022Carr Lane closed from junction with Chariot Street to junction with Queens Dock Avenue, 8pm-11.30pm daily. Diversion in place. About Us event
Charles Street04 April 202220 May 2022Works between Francis Street and Bridlington Avenue, including work in the carriageway and footpath. Removal of existing line markings, installation of new gullies and kerbs to construct off-road cycle track. New surfacing and line markings. Multi-way signals, to be manned at peak times. HCC - MP&I
Great Union Street23 May 202226 June 2022Resurfacing / concrete repairs. Full road closure. Access to be maintained at all times for businesses via A63 / Clarence Street.HCC - MP&I
Hessle Road (12-month Scheme)23 August 202104 September 2022Footway reconstruction.HCC - MP&I
High Street11 May 202212 May 2022Re-lay kerbs. Stop & Go signs. Work between 7.30am and 3.30pm.MP&I - ST GROUP LTD
Holderness Road (Victor St to Southcoates) (PHASES 1-8)04 January 202211 September 2022Full footway reconstruction scheme.MP&I - Highways Strategy & Design
Holwell Road11 May 202211 May 2022Telecoms maintenance. Two-way signals. Works between 9.30am and 3.30pm.T-Mobile
Hopewell Road14 March 202205 May 2022Concrete repairs and carriageway resurfacing. Road closure from Slaveley Road junction to Taylor Avenue.HCC - MP&I
Howdale Road - Phase 216 May 202227 May 2022Date changed. Trench repair on 2nd half of carriageway. Multi-way signals. Junction of Oaktree Drive. 8am start on Sunday. Traffic management to be removed once concrete has cured.Streetscene Highway Operations
Ings Road09 May 202219 May 2022Lane closure in place entrance between 9am and 3pm from the junction of Eglington Avenue to Crooked Billet car park entrance.Northern Gas Network
Mount Pleasant07 May 202209 May 2022Installation of duct crossing on Mount Pleasant between Wilmington waste disposal site and James Reckitt Avenue junction. Traffic signals from 7.30am on Saturday May 7, to be removed before 6am on Monday May 9.HCC - Colas
National Avenue18 May 202228 May 2022New power supply outside Caradon Heating. Two-way signals.Northern Powergrid
Paragon Street - About Us Event23 April 202209 May 2022Paragon Street – from junction with Chariot Street to eastern end of road.About Us Event
Park Street06 June 202217 June 2022Replacement of gas main. Road closure. Westbound road closure (Caughey Street to Spring Bank). No access from Spring Bank. Access from Park Street to Spring Bank still available.Northern Gas Network
Princes Avenue25 May 202227 May 2022Surfacing and line marking. Two-way signals in place 24 hours a day.HCC - MP&I
Priory Way01 April 202231 March 2023Major improvement scheme.HCC - MP&I
Stoneferry Rd Scheme - Woodhall Street to Lorraine Street01 April 202101 August 2022Major Improvement Scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall Street junction are now completed.HCC - MP&I
Stoneferry Rd Scheme - Chamberlain Road to Bandstand Roundabout23 April 202101 August 2022Major improvement scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall Street junction are now completed.HCC - MP&I / Colas
Stoneferry Rd Scheme - Leads Road25 April 202229 July 2022Renew footpaths and kerbs. Leads Road closed westbound between Rotterdam Road and Bandstand Roundabout during works.

HCC - MP&I / Colas
Stoneferry Rd Scheme - Leads Road29 July 202201 August 2022Carriageway resurfacing. Leads Road closed in both directions between Rotterdam Road and Bandstand Roundabout from 7pm on Friday 29 July to 6am on Monday August 1.HCC - MP&I / Colas
Stoneferry Rd Scheme - Sutton Road03 May 202201 July 2022Reconstruction of the new junction under temporary traffic lights to enable removal of the existing permanent traffic signals. Multi-way signals to run in phases to help minimise disruption. Leads Road / Sutton Road junction.HCC - MP&I