Weekly traffic and travel update – 4 August

Here is the latest breakdown of scheduled and emergency works taking place across Hull over the next few weeks. All works are subject to change. For the latest updates:

LocationStart dateDue dateSummary of worksUtility/HCC
A63 improvement scheme – St James Street to Market Place01-May-2001-May-25Lane and road closures until completion of scheme. National Highways
A63 improvement scheme – Commercial Road26-Oct-2130-Apr-24Enable H&S and safe systems of works for operatives working on the scheme. Road closure in place.National Highways
Alfred Gelder Street04-Aug-2308-Aug-23Emergency works to upgrade the electric connection for the Hull Maritime Museum refurbishment. Two-way signals in place at the junction of Guildhall Road.Harlaxton Energy Networks Limited
Boothferry Road31-Jul-2318-Aug-23Trial holes to the check the condition of Boothferry Footbridge under the carriageway from the central junction between Anlaby Park Road north and south. Road closure in place.Hull City Council (Bridges Team)
Beverley Road – Brunswick Arcade04-Oct-2101-Sep-23Brunswick Arcade demolition. Lane closures.Hull City Council (Major Projects)
Beverley Road01-Aug-2308-Sep-23Surfacing, lining, anti-skid and traffic signals at the junction of Queens Road.Hull City Council (Major Projects)
Beverley Road11-Sep-2302-Oct-23Telecoms duct installation at the junction of Beresford Avenue. Multi-way signals in place.Grain
Calvert Lane08-Aug-2310-Aug-23Remedial works to carriageway. Two-way signals in place from 9.30am to3.30pm.KCOM
Chanterlands Avenue10-Aug-2321-Aug-23Telecoms duct installation at the junction of Murrayfield Avenue. Multi-way signals in place from 9.30am to 3.30pm.
MS3
Gibraltar Road07-Aug-2311-Aug-23Telecoms upgrade works – pole and cabinet Swap. Road Closure one night only (Wednesday 9 – Thursday 10 – 8pm to 6am). Some carriageway incursion throughout the rest of the works.
Cornerstone Telecommunications Infrastructure ltd
Holderness Road24-Jul-2302-Aug-23Telecoms Pole Installation from Laburnum Avenue to the junction of Brindley Street. Lane closure in place from 9.30am to 3.30pm.MS3
Hall Road06-Aug-2307-Aug-23Swapping exsisiting telecoms pole for new telecoms pole. Overnight road closure in place from 8pm to 4am. Cornerstone Telecommunications Infrastructure ltd
Hall Road04-Aug-2309-Aug-23Swapping existing telecoms chamber for new telecoms chamber. Lane closure in place.
Cornerstone Telecommunications Infrastructure ltd
Holderness Road03-Aug-2311-Aug-23Telecoms duct installation and foot-way chambers from the junction of Brindley Street to the junction of Kingslsey. Lane closure in place from 9.30am to 3.30pm.
MS3
Humber Place11-Aug-2313-Aug-23Humber Street Sesh. Full road closure.Event
Humber Street12-Aug-2313-Aug-23Humber Street Sesh. Road closure from High Street to Queen Street.Event
High Street12-Aug-2313-Aug-23Humber Street Sesh. Road closure from Blackfriargate to Humber Street.Event
Hall Road14-Aug-2324-Aug-23Telecoms duct installation. Multi-way signals in place from 9.30am to 3.30pm.Connexin Ltd
James Reckitt Avenue31-Jul-2310-Sep-23Carrigeway reconstruction. Road closure.Hull City Council (Major Projects)
Lime Street13-Aug-2315-Aug-23The installation of a new boiler being put into Finlays Hull Ltd. Road closure in place from 8am to 5pm.Hull City Council
Nelson Street11-Aug-2313-Aug-23Humber Street Sesh. Road closure from Queen Street to Wellington Street.Event
Park Street23-Jul-2304-Aug-23Cable mains fault at the junction of Spring Bank. Road closure in place.Northern Powergrid
Priory Way14-Aug-2318-Aug-23Removal of old anti-skid and replace with new. Lane closures from Saxon Way to Sainsbury Way.Hull City Council (Major Projects)
Princes Road14-Aug-2301-Sep-23Gas mains replacement. Road closure in place between Lambert Street and De Grey Street from 8am to 5pm.Northern Gas Network
Percy Street14-Aug-2315-Sept-23Footway improvement works. Road closure in place.Hull City Council (Major Projects)
Queens Dock Street08-Aug-2311-Aug-23Emergency works to upgrade the electric connection for the Hull Maritime Museum refurbishment. Multi-way signals in place outside Hull Maritime Museum.Harlaxton Energy Networks Limited
Queen Street11-Aug-2313-Aug-23Humber Street Sesh. Road closure from Blanket Row to Nelson Street.Event
Springbank07-Aug-2318-Aug-23Telecoms duct installation. Lane closure from 9.30am to 3.30pm.MS3
Staveley Road12-Jun-2320-Aug-23Carriageway reconstruction between Greenwich Avenue and Barham Road. Road closure in place.Hull City Council (Major Projects)
Spring Bank West19-Aug-2320-Aug-23Uplift Walton Street level crossing for rail corrosion inspection and associated works. Road closure in place from 11.30pm to 8.30am.Network Rail
Swann Street25-Aug-2325-Aug-23Cherry picker to access telecoms mast for testing and maintenance works at the junction of Lincoln Street. Six hour road closure from 9.30am to 3.30pm.Hull City Council
Southcoates Avenue15-Aug-2304-Sep-23Excavate to install cable, joint new cable, transfer services. Multi-way signals in place from 8am to 4pm.Northern Powergrid
Wincolmlee26-Jul-2301-Aug-23Burst water main at the junction of Air Street. Road closure in place.Yorkshire Water
Wellington Street9-Aug-2314-Aug-23Humber Street Sesh. Full road closure.Event
Wingfield Road22-May-2320-Aug-23Carriageway reconstruction, concrete repairs/reconstruction. Rolling closure of whole street, access maintained for residents.Hull City Council (Major Projects)
Witty Street
07-Aug-2325-Aug-23Gas main replacement at the junction of Brighton Street. Road closure in place.Northern Gas Networks