Roadworks are to take place in Hull.
Essential repairs to Willerby Road will be carried out later this year.

Weekly roadworks update – February 4

Next week, part of Hessle (High) Road will be closed inbound to allow Yorkshire Water to carry out work in the carriageway.

The works are taking place on the approach to the Priory Way roundabout and are due to start on Monday February 7.  The work is expected to last one week.

Inbound traffic will be diverted via First Lane. Emergency access will be maintained.

Below is a breakdown of roadworks taking place across Hull over the next few weeks. All works are subject to change, so motorists are also advised to check one.network for the latest updates, as well as detailed maps and diversion routes.

LocationStart DateDue DateReasonUtility/HCC Name
A63 improvement scheme - Commercial Road26 October 202130 April 2022Enable H&S and safe systems of works for operatives working on the schemeNational Highways
A63 improvement scheme - St James Street to Market Place01 May 202001 May 2025Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre.National Highways
Barham Road29 November 202106 February 2022Carriageway resurfacing and concrete repairs.HCC - MP&I
Bellfield Avenue10 January 202211 April 2022Multi-way signals at the junction with Savoy Road. Manned between traffic sensitive times.HCC - MP&I
Beverley Road - Brunswick Arcade04 October 202101 September 2022Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022.HCC - MP&I
Beverley Road - Mizzen Road to Windle Avenue05 January 202211 February 2022Construction of new cycle track and footpath on the existing footpath and verge. Lane closure.MP&I ARBPMLTD
Bowlalley Lane14 February 202228 February 2022Road closure to reinstate carriageway gas trenching and install raised table. Local diversion in place to allow acces for residents / businesses.HCC - MP&I
Haller Street05 February 202205 February 2022Major non-excavation works. Road closure for work to take place from 10am to 3.30pm. Further information to be sent to nearby residents one week prior to works.T-Mobile (UK) Ltd (Ericsson)
Hessle Road (12-month Scheme)23 August 202104 September 2022Footway reconstruction.HCC - MP&I
Hessle Road07 February 202214 February 2022Installation of sewer pipe. Inbound closure only near junction of Priory Way. Local diverson in place.Section 278 Development
Holderness Road (Victor St to Southcoates) (PHASES 1-8)04 January 202211 September 2022Full footway reconstruction scheme.MP&I - Highways Strategy & Design
Holderness Road24 January 202211 February 2022Excavation for new cable connection.Northern Powergrid
Holwell Road15 February 202217 February 2022Land and erect new streetworks pole on the grass verge on Holwell Road 20m from junction with Goodhart Road. Multi way signals. Two-way pedestrian light with marshalls to be used when lifting is in progres. Working hours will be 8am-6pmVodafone
Hopewell Road14 March 202224 April 2022Concrete repairs and carriageway resurfacing. Road closure from Slaveley Road junction to Taylor Avenue.HCC - MP&I
Hopewell Road Roundabout08 February 202209 February 2022Repairs to the existing concrete surface and joints of the roundabout. Lane closure will commence at 0930 on Tues 8 Feb and remain in place for the duration of the works. TM will be removed where possible when the repairs are safe to traffic.HCC - MP&I COLAS
Humber Street07 February 202219 March 2022Installation of bollards. Works span width of footway and carriageway outside Dinostar. Work will be done in sections to maintain pedestrian walkway.HCC - MP&I
Lowgate Footway Scheme - West / East Footway22 October 202116 April 2022Footway repair scheme. Scheme delayed due to signal failure on A63. Current traffic management set-up (northbound closure) to remain in place for duration of scheme.HCC - MP&I
Marfleet Avenue07 February 202209 February 2022Carriageway repair works at junction of Marfleet Avenue leading to Marfleet Lane. Three-way lights. Works to take place for one day only from 9.30am-3.30pm.HCC - Highway Operations
Marfleet Lane21 February 202223 February 2022Carriageway repair works (sunken trench). Multi-way signals. On top of the railway bridge. Works to take place for one day only from 9.30am-3.30pm.HCC - Highway Operations
Preston Road07 February 202216 February 2022Bus stop relocation. Narrowing of central reserve to give 3m-width traffic lane; slip trench on the central reserve. Lane closure to start at 9.30am on first day of works.HCC - Bridges
Silver Street04 January 202213 February 2022Road closure due to installation of automated bollards.HCC - MP&I
Staveley Road07 February 202209 February 2022Multiple carriageway repair works at multiple locations. Multi-way signals to be used for each separate works. Works to take place for one day only from 9.30am-3.30pm.HCC - Highway Operations
Stoneferry Rd Scheme - Woodhall Street to Lorraine Avenue01 April 202101 April 2022Major Improvement Scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completedHCC - MP&I
Stoneferry Rd Scheme - Chamberlain Road to Bandstand roundabout23 April 202101 April 2022Major improvement scheme commissioned by HCC - Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completedHCC - MP&I / Colas
Sutton Road14 February 202224 February 2022Installation of duct crossings for new traffic signals at junction of Leads Road /Sutton Road. Multi-way signals. works to take place between 7.30pm-6am. Carriageway will be clear at all other times.HCC - MP&I COLAS
Wincolmlee (Phase 2)31 January 202204 March 2022Road closure for new connection and cable upgrades.Northern Powergrid
Wold Road (Phase 1)02 February 202206 February 2022Excavations in preparation of installation of 5G telecoms tower at junction with Willerby Road and Seagrave Grove. Work from 9.30am 3.30pm. Multi-way signals in place for short durations. Carriageway to be clear at all other times.T-Mobile
Wold Road (Phase 2)28 February 202204 March 2022Install new telecoms pole at junction with Willerby Road and Seagrave Grove. Work from 9.30am to 3.30pm. Multi-way signals in place for short durations. Carriageway to be clear at all other times.T-Mobile