Weekly Roadworks Update – 1 October

Weekly roadworks update – 1 October

This week it was announced that essential overnight resurfacing works will be taking place from Monday 18 October as part of the multi-million-pound Stoneferry improvement scheme.

The works are expected to last around two weeks and will be undertaken overnight in order to minimise disruption.

Councillor Dean Kirk, Portfolio Holder for transportation, roads and highways said: “The fact that these closures are being done overnight will ensure that this stage of the works can be completed as quickly and efficiently as possible. We are another step closer to improving access and use for thousands of residents and businesses in the area.

“Noise mitigation has been a core consideration in the selection of equipment and we apologise for any inconvenience caused as we aim to complete these works as swiftly as possible.”

Read more, here.

A breakdown of planned works taking place across the city has been detailed below:

 

Location Start date Completion date Details of work Organisation Current status
A63 Castle Street – From St James Street to Market Place

 

May 2020 May 2025 Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGV’s in city centre. National Highways On track
A63 Castle St Scheme – Closures May 2020 May 2025 Full lane closures east & west bound. Highways England Planned
Stoneferry Rd Scheme  – Woodhall Street to Lorraine Ave Commenced 28 May 2022 Installation of the Stoneferry Road corridor capital program scheme HCC MP&I (Colas) On track
Stoneferry Rd Scheme
Woodhall Street to Chamberlain Road
4 October 2021 16 October 2021 Relocation of gully’s Hull City Council, MP&I Planned
 Stoneferry Rd Scheme – Chamberlain Road to Bandstand Roundabout 23 April 2021 25 June 2022 Installation of the Stoneferry Road Corridor Hull City Council, MP&I Ongoing
Stoneferry Rd Scheme –  Sutton Road /Leads Road June 2021 Awaiting update Reconstruction of junction. F/Way Only – Stoneferry Corridor works Hull City Council, MP&I Ongoing
Stoneferry Corridor – Resurfacing full scheme 20 Sept  2021 Jan 2021 Carriageway resurfacing throughout the whole scheme Hull City Council, MP&I Planned
Stoneferry corridor  – Woodhall Street to Chamberlain Road 18 October 21 29 October 21 Re construction of the carriageway Hull City Council, MP&I Delayed
Wiltshire Road (full length)

 

14 June 21 17 Oct 21 – now extended by 8 weeks Excavate existing concrete carriageway and carry out any required concrete repairs. HCC – MP&I Extended by 8 weeks
A63 Commercial Road 2 August 2021 25 October 2021 A63 Improvement scheme National Highways On track
Brunswick Arcade (Beverley Road) 16 August 2021 November 2022 Lane closures from October 2021 onwards Hull City Council On track
Lowgate 20 September 2021 25 March 2022 Paving of footpaths Hull City Council Planned
Queen Street/Blankett Row 27 September 2021 10 October 2021 Resurfacing scheme Hull City Council On track
Inglemire Lane & Hall Road 27 September 2021 10 October 2021 Road resurfacing – temp traffic lights Hull City Council On track
Priory Way

 

October 2021 August 2022 Major widening and construction of three signalised junctions Hull City Council Planned
Spring Bank West 19 July 2021 1 October 2021 Essential gas works NGN Extended to 1 October
Commercial Road

 

2 August 2021 25 October 2021

 

A63 improvement scheme Highways England On track
Beverley Road LEP (Whole length – split into phases as shown below) 23 August 2021 December 2021 Create cycle lanes & junction widening Hull City Council,  MP&I Started
Beverley Road

(Phase 1)

23 August 2021 8 October 2021 – extended, awaiting update Construction of off lane cycle track. Greenwood Avenue to Hall Road Outbound. Hull City Council,  MP&I Started
Beverley Road
(Phase 2)
6 September 2021 8 October 2021 – extended, awaiting update Wellington Street outbound to Cave Street Hull City Council,  MP&I Planned
Beverley Road

(Phase 3)

21 September 2021 13 October 2021 Construction of off line cycle track. Greenwood Avenue to City Boundary Outbound Hull City Council,  MP&I Planned
Beverley Road

(Phase 4)

22  August 2021 17 November 2021 Construction of off line cycle track. Mizzen Road to Hall Road Inbound Hull City Council,  MP&I Planned
Beverley Road

Inbound – Phase 1

31 August 2021 21 October 2021 Construction of Cycle Way Hull City Council,  MP&I Planned
Bowl Alley Lane October 2021 October 2021 Pavement improvements – road closure Hull City Council Planned
Air Street 27 September 2021 22 October 2021 Essential gas work upgrades NGN Planned
Silver Street 4 January 2022 31 January 2022 Installing automatic bollards Hull City Council Planned
Holderness Road
Victor Street to Southcoates – Phases 1-8
27 September 2021 September 2022 Full footway reconstruction scheme Hull City Council,  MP&I Planned
Gillshill Road 21 September 2021 6 October 2021 Water Leak Yorkshire Water Early completion anticipated