Here is the latest breakdown of scheduled and emergency works taking place across Hull over the next few weeks. All works are subject to change. For the latest updates:
- Visit National Highways for more information on planned roadworks, or follow them on Twitter @HighwaysYORKS
- Follow @hullccnews on Twitter
- Follow the Hull City Council Facebook page
- Check one.network before travelling.
A63 improvement scheme – St James Street to Market Place | 01-May-20 | 01-May-25 | Full infrastructure change. Lane and road closures until completion of scheme. | National Highways |
A63 improvement scheme – Commercial Road | 26-Oct-21 | 30-Apr-24 | Enable H&S and safe systems of works for operatives working on the scheme. Road closure in place. | National Highways |
A63 Castle Street – between Daltry Street and Roger Millward Way | 10-Mar-24 | 06-April-24 | Various overnight closures to complete work at Market Place and Queen Street junction and other essential works. To find our more, visit https://nationalhighways.co.uk/our-roads/yorkshire-and-north-east/a63-castle-street/ | National Highways |
Alexandra Road | 05-Feb-24 | 18-Mar-24 | Carriageway reconstruction and resurfacing from Beverley Road to Leonards Avenue. Road closure in place. | Hull City Council (Major Projects) |
Cleveland Street | 08-Mar-24 | 08-Mar-24 | Cutting of new detection loop damaged by on going work. Multi-way signals in place. | Hull City Council (Major Projects) |
County Road North | 4-Mar-24 | 16-Mar-24 | To strengthen and repair the existing structure. Two-way signals in place. | Hull City Council (Bridges Team) |
Coventry Road | 04-Mar-24 | 17-May-24 | Installing a new pipe, manhole and connecting onto the existing combined sewer network. Part of the Living with Water Aqua Green Scheme. Road closure in place. | Yorkshire Water |
Manor Road | 05-Feb-24 | 26-April-24 | Installing a new pipe, manhole, and connecting onto the existing combined sewer network outside number 82 and 84. Part of the Living with Water Aqua Green Scheme. Road closure in place. | Yorkshire Water |
Moorhouse Road | 11-Mar-24 | 14-Jun-24 | Installing a new pipe and manhole on the carriageway and connecting onto the combined sewer. Part of the Living with Water Aqua Green Scheme. Road closure in place. | Yorkshire Water |
Spring Bank | 05-Mar-24 | 07-Mar-24 | Re-new leaking water supply pipe. Lane closure in place. | Yorkshire Water |
Spring Bank West | 04-Mar-24 | 12-Mar-24 | Telecoms Installation at the junction of Albert Avenue. Lane closure in place. | Grain |
Wingfield Road | 26-Feb-24 | 11-Mar-24 | Carriageway reconstruction. Traffic control (priority working) in place. | Hull City Council (Major Projects) |